City of Mesa (AZ)
Codes
- NEC Code Version
- 2017
- Fire Code Version
- 2018 Building Code
- Code List
2018 INTERNATIONAL BUILDING CODE
2018 INTERNATIONAL RESIDENTIAL CODE
2018 INTERNATIONAL FIRE CODE
2018 INTERNATIONAL PLUMBING CODE
2017 NATIONAL ELECTRICAL CODE
2018 INTERNATIONAL MECHANICAL CODE
2018 INTERNATIONAL FUEL GAS CODE
2018 INTERNATIONAL EXISTING BUILDING CODE
2018 INTERNATIONAL ENERGY CONSERVATION CODE
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- SolarAPP+ Status
- Targeted
- Any SolarAPP+ Restrictions
- 1
- SolarAPP+ Restrictions
- MPU,Derate
- How Many Plansets Required
- Other (See Submission Notes)
- Revision Required
- 1
- New Planset Required For Module Swap
- 1
Stamps
- Ee Stamp Required On SLD
- Yes
- Wet Stamps Required
- Digital Structural,Digital Electrical
- Structural Calculations Required
- Yes
- Ee Stamp Notes
EE Stamps are needed for SRP Utility whenever the AHJ does not require a permit, such as any system without an MPU.
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
Standard
Structural & loads
- Wind Speed
- 100
- Wind Notes
Exposure Category B
- Snow Load
- 0
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Structural Notes
- Minimum Ground On Roof
- #10
Electrical
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Line Side Taps,PV Breaker,Load Side Taps,Meter Adapter
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 0.87
Battery / ESS
- Unique Battery Placards Needed
- 1
- ESS Notes
- Separate ESS Disconnect Required
- Local Disconnect
- ESS Elevation Detail Required
- No
Plan set
- Plan Set Requirements
No red fonts or red clouds allowed on plan sets. Change colors to black before submitting.
* NO PERMITS REQUIRED FOR SOLAR SYSTEMS IN CITY OF MESA. * IF A NEW SES OR MPU IS REQUIRED, A MESA PERMIT AND CLEARANCE/GREEN TAG (JUST FOR THE NEW SES) IS REQUIRED * Flatten PDFs before uploading.
- Site
SRP requirements, include (E) (1 OF 2) (2 OF 2) for all -DEDICATED DER METER
-DER METER DISCONNECT SWITCH
-UTILITY AC DISCONNECT SWITCH
-(N)(E) modules to be shown on placard page
- Electrical Diagram
Centerfed 120% allowed
City of Mesa/MesaAZ utility follow SRP labeling for all PMs and disconnects
-DEDICATED DER METER
-DER METER DISCONNECT SWITCH
-UTILITY AC DISCONNECT SWITCH
- Label Page Notes
SRP requirements, include (E) (1 OF 2) (2 OF 2) for all -DEDICATED DER METER
-DER METER DISCONNECT SWITCH
-UTILITY AC DISCONNECT SWITCH
-(N)(E) modules to be shown on placard page
- Custom Placards Required
- 0
- Non Standard Revision Requirements
No red clouds or deltas. Change to black.
Ground mount
- Ground Mount Fencing Required
- No