City of Lakeport (CA)
Codes
- NEC Code Version
- 2023
- Fire Code Version
- 2018 Building Code
- Code List
2025 CALIFORNIA BUILDING CODE
2025 CALIFORNIA ELECTRICAL CODE
2025 CALIFORNIA FIRE CODE
2025 CALIFORNIA PLUMBING CODE
2025 CALIFORNIA MECHANICAL CODE
2025 CALIFORNIA ENERGY CODE
2025 CALIFORNIA RESIDENTIAL CODE
2025 CALIFORNIA ADMINISTRATIVE CODE
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- How Many Plansets Required
- 2
- Revision Required
- 0
- New Planset Required For Module Swap
- 0
Stamps
- Structural Calculations Required
- No
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
Standard
Structural & loads
- Wind Speed
- 110
- Wind Notes
Exposure Category B
- Snow Load
- 10
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Minimum Ground On Roof
- #10
Electrical
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Meter Adapter,Load Side Taps,Line Side Taps,PV Breaker
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 0.91
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
Required to provide complete dimensions of entire wall (length/height), all openings (windows/doors/vents), equipment and locations of equipment for 'energy storage systems'.
If battery system, include this note on ELD: Producer's storage device(s) will not cause the Host Load to exceed its normal peak demand. Normal peak demand is defined as the highest amount of power required from the Distribution System by Producer's complete facilities without the influence or use of the energy storage device(s).
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- No
Plan set
- Plan Set Requirements
Per building official - Tom: load calculations for de-rates are generally not required the new mid-cycle fire code is accepted from CRC Design Criteria link (https://www.cityoflakeport.com/community_development/building/design_criteria.php)
- Roof Plan
The dimensions of the roof must be shown as well as the dimensions of the solar arrays. Example of roof and panel dimensions is uploaded to the files below.
- Electrical Diagram
120% rule allowed per CEC 705.12(B)(2)(3)(d)
- Custom Placards Required
- 1
Ground mount
- Ground Mount Fencing Required
- Mesh/Scrim