City of Rancho Santa Margarita (CA)

California Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2023
Fire Code Version2018 Building Code
SolarAPP+ StatusAdopted
Wet Stamps RequiredNone
Fire Setback Enforced1

Codes

NEC Code Version
2023
Fire Code Version
2018 Building Code
Code List

2025 CALIFORNIA BUILDING CODE

2025 CALIFORNIA ELECTRICAL CODE

2025 CALIFORNIA FIRE CODE

2025 CALIFORNIA PLUMBING CODE

2025 CALIFORNIA MECHANICAL CODE

2025 CALIFORNIA ENERGY CODE

2025 CALIFORNIA RESIDENTIAL CODE

2025 CALIFORNIA ADMINISTRATIVE CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

SolarAPP+ Status
Adopted
Any SolarAPP+ Restrictions
1
SolarAPP+ Restrictions
Existing Systems,Trenching
How Many Plansets Required
3
Revision Required
1
Rough Inspection
None
New Planset Required For Module Swap
1

Stamps

Wet Stamps Required
None
Structural Calculations Required
Yes
Stamp Location On Plans
Unspecified
Date On Stamps
Expiration Date

Fire setbacks

Fire Setback Enforced
1
Setback Notes

Standard

Structural & loads

Wind Speed
110
Wind Notes

Exposure Category C

Snow Load
0
Reducible Snow Load Allowed
1
Max Attachment Spacing
96
Structural Notes

Please provide structural calcs

Minimum Ground On Roof
#10

Electrical

AC Disconnect Required
Yes
Electrical Load Calcs Required
Derates
Allowed POI
Line Side Taps,Load Side Taps,Meter Adapter,PV Breaker
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
0.96

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

Standard

ESS disconnect required within 6ft of MSP on same wall and not blocked by walls/gates/etc

Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
Yes - with dimensions

Plan set

Plan Set Requirements

Detail the location of the gas meter (3' clearance)



If MSP is rated 125A or below, electrical load calcs are required.


Need to show 3' Clearance from gas meter to any new electrical equipment for expedited submittals under 10 kW, submittals should have the Eligibility Checklist, Structural Checklist, and Standard Plan.



Site

Gas Meter: Must maintain 3' clearance, show location on the Site Plan.

Roof Plan

Fire Setbacks: 3' Setback required around chimneys, no exception even if fire pathway does not go through a chimney.

Electrical Diagram

Load calcs required for all sub panels/load centers

Custom Placards Required
1

Ground mount

Ground Mount Fencing Required
Mesh/Scrim
Compiled from public records, 2026. Requirements change with code cycles and local amendments. Verify with the City of Rancho Santa Margarita (CA) building department before you rely on this, and treat it as a research head start, not a ruling. Getting quotes? Run them through the quote checker first.