City of San Bruno (CA)

California Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2023
Fire Code Version2018 Building Code
SolarAPP+ StatusAdopted
Wet Stamps RequiredDigital Structural
Fire Setback Enforced1

Codes

NEC Code Version
2023
Fire Code Version
2018 Building Code
Code List

2025 CALIFORNIA BUILDING CODE

2025 CALIFORNIA ELECTRICAL CODE

2025 CALIFORNIA FIRE CODE

2025 CALIFORNIA PLUMBING CODE

2025 CALIFORNIA MECHANICAL CODE

2025 CALIFORNIA ENERGY CODE

2025 CALIFORNIA RESIDENTIAL CODE

2025 CALIFORNIA ADMINISTRATIVE CODE

IEBC Accepted
1
ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

SolarAPP+ Status
Adopted
Any SolarAPP+ Restrictions
1
SolarAPP+ Restrictions
Existing Systems,Trenching
How Many Plansets Required
3
Revision Required
1
Rough Inspection
None
New Planset Required For Module Swap
0

Stamps

Wet Stamps Required
Digital Structural
Structural Calculations Required
Yes - Attachment Spacing > 6ft
Stamp Location On Plans
Top Right

Fire setbacks

Fire Setback Enforced
1
Setback Notes

Standard

Structural & loads

Wind Speed
110
Wind Notes

Exposure Category B

Snow Load
0
Reducible Snow Load Allowed
1
Max Attachment Spacing
96
Minimum Ground On Roof
#10

Electrical

AC Disconnect Required
Yes
Electrical Load Calcs Required
Derates
Allowed POI
Meter Adapter,PV Breaker,Line Side Taps,Load Side Taps
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
1

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

Elevation drawing: Please clearly indicate the 3-feet clearance from windows and doors per CFC 1207.11.13

Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
Yes

Plan set

Plan Set Requirements

STANDARD

Cover Page


Cover Page Notes

AHJ Wants Cover page note:


1 - Occupancy Group: R-3/U

2 - Construction Type: V-B

3 - Number of Stories:

4 - Fire Sprinklers: Y/N

Roof Plan Notes

All Jobs [Modules will not cover plumbing or exhaust vents.]

Electrical Diagram


Electrical Diagram Notes

All Jobs [All conductors to be copper. // Solar breaker shall be placed opposite of main breaker on bus bars.]

Custom Placards Required
1

Ground mount

Ground Mount Fencing Required
Mesh/Scrim
Compiled from public records, 2026. Requirements change with code cycles and local amendments. Verify with the City of San Bruno (CA) building department before you rely on this, and treat it as a research head start, not a ruling. Getting quotes? Run them through the quote checker first.