City of San Pablo (CA)

California Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2023
Fire Code Version2018 Building Code
SolarAPP+ StatusAdopted
Wet Stamps RequiredNone
Fire Setback Enforced1

Codes

NEC Code Version
2023
Fire Code Version
2018 Building Code
Code List

2025 CALIFORNIA BUILDING CODE

2025 CALIFORNIA ELECTRICAL CODE

2025 CALIFORNIA FIRE CODE

2025 CALIFORNIA PLUMBING CODE

2025 CALIFORNIA MECHANICAL CODE

2025 CALIFORNIA ENERGY CODE

2025 CALIFORNIA RESIDENTIAL CODE

2025 CALIFORNIA ADMINISTRATIVE CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

SolarAPP+ Status
Adopted
Date SolarAPP+ Accepted
44798
Any SolarAPP+ Restrictions
1
SolarAPP+ Restrictions
Existing Systems,Trenching
How Many Plansets Required
3
Revision Required
0
New Planset Required For Module Swap
0

Stamps

Wet Stamps Required
None
Structural Calculations Required
No
Stamp Location On Plans
Unspecified
Date On Stamps
Expiration Date

Fire setbacks

Fire Setback Enforced
1
Setback Notes

Standard

Structural & loads

Wind Speed
110
Wind Notes

Exposure Category B

Snow Load
0
Reducible Snow Load Allowed
1
Max Attachment Spacing
96
Structural Notes
04/21/21 - Submit completed "San Pablo Structural Criteria Form". See Files section of this page. 03/18/2021 (HB) - Marking this as Sometimes since it was needed for the flat roof on "a past project - 1811 Pablo Vista." (These 2x10 rafters were spaced at 55", which is non-standard.) For now, avoid getting stamped plans if the structure is more typical than for the project noted here.
Minimum Ground On Roof
#10

Electrical

Electrical Load Calcs Required
Derates
Allowed POI
Line Side Taps,PV Breaker,Meter Adapter,Load Side Taps
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
1

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

Standard

Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Plan set

Plan Set Requirements

AHJ Requires 2 forms to be filled out, include them when uploading plans:

Photovoltaic - Structural Criteria_202104212132297174.pdf

Photovoltaic Expedited Permit_202104212131402951.pdf


if we are using a tilt-up kit, do not use the PZSE letter if it has the Clearance: 2 to 10 clear from top of roof to top of PV panel language or if it says FLUSH anywhere on it as the AHJ will see this as contradictory. Instead, use the [Unirac SM Low Profile Tilt State Letter 12-18-2020_CA_Stamped_Cert] in the files below. Submit completed San Pablo Structural Criteria Form. See Files section of this page.

Electrical Diagram

120% rule allowed per CEC 705.12(B)(2)(3)(d)

Custom Placards Required
1

Ground mount

Ground Mount Fencing Required
Yes
Ground Mount Notes

Array must be 3' from Back and Rear Property Lines. 6' from the Main home. 12' Max height Septic Documentation will be gathered from Public Works (not applicable for most homes)

Setback Front Yard
15
Compiled from public records, 2026. Requirements change with code cycles and local amendments. Verify with the City of San Pablo (CA) building department before you rely on this, and treat it as a research head start, not a ruling. Getting quotes? Run them through the quote checker first.