City of Vista (CA)

California Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2023
Fire Code Version2018 Building Code
SolarAPP+ StatusAdopted
Wet Stamps RequiredNone
Fire Setback Enforced1

Codes

NEC Code Version
2023
Fire Code Version
2018 Building Code
Code List

2025 CALIFORNIA BUILDING CODE

2025 CALIFORNIA ELECTRICAL CODE

2025 CALIFORNIA FIRE CODE

2025 CALIFORNIA PLUMBING CODE

2025 CALIFORNIA MECHANICAL CODE

2025 CALIFORNIA ENERGY CODE

2025 CALIFORNIA RESIDENTIAL CODE

2025 CALIFORNIA ADMINISTRATIVE CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

SolarAPP+ Status
Adopted
Any SolarAPP+ Restrictions
1
SolarAPP+ Restrictions
Existing Systems,Trenching
How Many Plansets Required
2
Revision Required
1
Rough Inspection
Fire Inspection
New Planset Required For Module Swap
1

Stamps

Ee Stamp Required On SLD
No
Wet Stamps Required
None
Structural Calculations Required
Yes
Stamp Location On Plans
Unspecified
Date On Stamps
Expiration Date

Fire setbacks

Fire Setback Enforced
1
Setback Notes


Structural & loads

Wind Speed
110
Wind Notes

Exposure Category C

Snow Load
0
Reducible Snow Load Allowed
1
Max Attachment Spacing
72
Structural Notes

Standard

Minimum Ground On Roof
#10

Electrical

Electrical Load Calcs Required
Derates
Allowed POI
Line Side Taps,PV Breaker,Meter Adapter,Load Side Taps
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
1

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

Standard

Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
Yes - with dimensions

Plan set

Electrical Diagram Notes

All Jobs [If the existing MSP does not have a verifiable grounding electrodes system, a grounding electrode system will be installed per CEC 250.50. The electrical service will be bonded to the water gas piping per Section 250.104 of CEC.]

Label Page

Placard should be rotated so that the BOS equipment is toward the bottom of the placard drawing.

Custom Placards Required
1
Placards Notes

Placard should be rotated so that the BOS equipment is toward the bottom of the placard drawing.

Ground mount

Ground Mount Fencing Required
Yes
Ground Mount Notes

Ground Mounts: With regard to fencing….we require that any conductors that may be incidentally contacted are protected from damage or tampering by unauthorized persons. This can be accomplished with fencing or approved metal conduit where no conductors are unprotected within reach proximity. **I spoke with Eddie - he confirmed that there is no way you can cover all of the wires with just conduit. Fencing is required.**