NEC Code Version2023
Fire Code Version2018 Building Code
SolarAPP+ StatusTargeted
Wet Stamps RequiredNone
Fire Setback Enforced1

Codes

NEC Code Version
2023
Fire Code Version
2018 Building Code
Code List

2025 CALIFORNIA BUILDING CODE

2025 CALIFORNIA ELECTRICAL CODE

2025 CALIFORNIA FIRE CODE

2025 CALIFORNIA PLUMBING CODE

2025 CALIFORNIA MECHANICAL CODE

2025 CALIFORNIA ENERGY CODE

2025 CALIFORNIA RESIDENTIAL CODE

2025 CALIFORNIA ADMINISTRATIVE CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

SolarAPP+ Status
Targeted
Any SolarAPP+ Restrictions
1
SolarAPP+ Restrictions
MPU,Derate
How Many Plansets Required
2
Revision Required
0
Rough Inspection
None
New Planset Required For Module Swap
0

Stamps

Wet Stamps Required
None
Structural Calculations Required
Yes
Stamp Location On Plans
Unspecified
Date On Stamps
Expiration Date

Fire setbacks

Fire Setback Enforced
1
Setback Notes

Standard

Structural & loads

Wind Speed
110
Wind Notes

Exposure Category C

Snow Load
999
Reducible Snow Load Allowed
1
Max Attachment Spacing
96
Structural Notes

Standard

Minimum Ground On Roof
#10

Electrical

Electrical Load Calcs Required
Derates
Allowed POI
PV Breaker,Load Side Taps,Meter Adapter,Line Side Taps
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
0.91

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

No published information about battery placement. If battery system, include this note on ELD: Producer's storage device(s) will not cause the Host Load to exceed its normal peak demand. Normal peak demand is defined as the highest amount of power required from the Distribution System by Producer's complete facilities without the influence or use of the energy storage device(s).

Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Plan set

Electrical Diagram

120% rule allowed

Custom Placards Required
1

Ground mount

Ground Mount Fencing Required
No
Ground Mount Notes

Building Setbacks in the Rural Residential (RR) zone are as follows: F: 20โ€™ S: 10โ€™ R: 20โ€™ Setback requirements vary by zone. Contact Planning Dept to confirm the specific setbacks. - The fire life safety setbacks of 30โ€™ from each property boundary apply to all parcels 1+ acres in size. Confirm with the County Building Department to see if fire, life and safety setbacks apply to your project. FEMA flood zone must be delineated on the site plan to confirm the structure is not in the flood zone. GIS shows the flood zone being approximately 160โ€™ from rear property. Site plan shows ground-mount solar being 156โ€™ from rear property line

Setback Front Yard
30
Setback Back Yard
30
Setback Side Yard
30