California Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2023
Fire Code Version2018 Building Code
SolarAPP+ StatusTargeted
Fire Setback Enforced1

Codes

NEC Code Version
2023
Fire Code Version
2018 Building Code
Code List

2025 CALIFORNIA BUILDING CODE

2025 CALIFORNIA ELECTRICAL CODE

2025 CALIFORNIA FIRE CODE

2025 CALIFORNIA PLUMBING CODE

2025 CALIFORNIA MECHANICAL CODE

2025 CALIFORNIA ENERGY CODE

2025 CALIFORNIA RESIDENTIAL CODE

2025 CALIFORNIA ADMINISTRATIVE CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

SolarAPP+ Status
Targeted
Any SolarAPP+ Restrictions
1
SolarAPP+ Restrictions
MPU,Derate
How Many Plansets Required
2
Revision Required
1
Rough Inspection
None
New Planset Required For Module Swap
0

Stamps

Ee Stamp Required On SLD
No
Structural Calculations Required
No

Fire setbacks

Fire Setback Enforced
1
Setback Notes

Standard

Structural & loads

Wind Speed
110
Wind Notes

Exposure Category C

Snow Load
40
Reducible Snow Load Allowed
1
Max Attachment Spacing
96
Structural Notes
No PE required
Minimum Ground On Roof
#10

Electrical

AC Disconnect Required
Yes
Electrical Load Calcs Required
Derates
Allowed POI
PV Breaker,Load Side Taps,Line Side Taps,Meter Adapter
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
0.91

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

On ELD:

Battery [Producer's storage device(s) will not cause the Host Load to exceed its normal peak demand. Normal peak demand is defined as the highest amount of power required from the Distribution System by Producer's complete facilities without the influence or use of the energy storage device(s).]

Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Plan set

Site

Need to show all structures, sheds, etc, with measurements

Electrical Diagram

Centerfed 120%: EE Stamp Required

Custom Placards Required
1

Ground mount

Ground Mount Fencing Required
Situational
Ground Mount Notes

Grounds screws are allowed but require special inspections per the listing. Considerations for ground mounts include the location of both the septic and well, and the setbacks from both that are required. There is no one size fits all requirement for these setbacks because we have various types of systems with differing setbacks. If you have a specific property that you are working on we can supply you with a copy of our plot plan with the septic location and a list of the appropriate setbacks for that system. In regards to plan submittals we require that all plot plans have the septic and well indicated and the distances to the solar array be marked. Beyond plot plans and locations we have a few other things we require; no driving/storing materials on the leach field and no trenching through the leach field/repair area/sand filter. When the project is within a special flood hazard zone, the electrical panels and equipment must be at least 5 feet above the highest adjacent grade. ****For requesting septic map / plot plans**** * **** * **Community Development & Seervices Agency** * **Yuba County Environmental Health**