City and County Broomfield (CO)
NEC Code Version2023
SolarAPP+ StatusTargeted
Wet Stamps RequiredDigital Structural,Digital Electrical
Fire Setback Enforced0
Codes
- NEC Code Version
- 2023
- Code List
2023 NATIONAL ELECTRICAL CODE
2021 INTERNATIONAL FIRE CODE
2021 INTERNATIONAL PLUMBING CODE
2021 INTERNATIONAL MECHANICAL CODE
2021 INTERNATIONAL RESIDENTIAL CODE
2021 INTERNATIONAL BUILDING CODE
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- SolarAPP+ Status
- Targeted
- Any SolarAPP+ Restrictions
- 1
- SolarAPP+ Restrictions
- MPU,Derate
- How Many Plansets Required
- 1
- Revision Required
- 1
- Rough Inspection
- None
- New Planset Required For Module Swap
- 1
Stamps
- Ee Stamp Required On SLD
- Yes - 10kW+
- Wet Stamps Required
- Digital Structural,Digital Electrical
- Structural Calculations Required
- Yes
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 0
- Setback Notes
No setbacks
Structural & loads
- Wind Speed
- 145
- Wind Notes
Exposure Category C
- Snow Load
- 30
- Snow Load Notes
30 PSF
- Reducible Snow Load Allowed
- 0
- Max Attachment Spacing
- 96
- Structural Notes
For the city of Broomfield we'll need to obtain a PE stamped letter of approval for our customers roof calculations
- Minimum Ground On Roof
- #6
Electrical
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Load Side Taps,Meter Adapter,Line Side Taps,PV Breaker
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 0.96
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
Standard
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- No
Plan set
- Plan Set Requirements
Please verify that the modules are installed that there are no vents covered by modules.
- Cover Page
TITLEBLOCK: License #: both EC & ME
- Roof Plan
Please verify that the modules are installed that there are no vents covered by modules.
- Electrical Diagram
- #6 Ground only required from optimizer to Jbox
- For projects where a PV meter is required by the utility and the POI is a tap: provide a fused disconnect between the MSP and the PV meter, and an unfused disconnect between the PV meter and the inverter.
- Custom Placards Required
- 0
Ground mount
- Ground Mount Fencing Required
- No
- Ground Mount Notes
Soil Class: Clay
GMs no longer allowed in front of home; must be 10ft behind dwelling as of 3/5/2025
- Ground Mount Requires Soil Sample
- Soil Study