City of Arvada (CO)

Colorado Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2023
Fire Code Version2018 Building Code
SolarAPP+ StatusTesting
Wet Stamps RequiredDigital Structural,Digital Electrical
Fire Setback Enforced1

Codes

NEC Code Version
2023
Fire Code Version
2018 Building Code
Code List

2018 INTERNATIONAL BUILDING CODE

2018 INTERNATIONAL FUEL GAS CODE

2018 INTERNATIONAL PLUMBING CODE

2018 INTERNATIONAL ENERGY CODE

2018 EXISTING BUILDING CODE

2018 INTERNATIONAL RESIDENTIAL CODE

2018 INTERNATIONAL MECHANICAL CODE

2009 INTERNATIONAL PROPERTY MAINT. CODE

2018 INTERNATIONAL FIRE CODE

2023 NATIONAL ELECTRIC CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

SolarAPP+ Status
Testing
Any SolarAPP+ Restrictions
1
SolarAPP+ Restrictions
MPU,Derate
How Many Plansets Required
1
Revision Required
1
Rough Inspection
None
New Planset Required For Module Swap
1

Stamps

Ee Stamp Required On SLD
Yes
Wet Stamps Required
Digital Structural,Digital Electrical
Structural Calculations Required
Yes
Ee Stamp Notes

Per recent AHJ kickbacks all plans required Electrical Engineer Stamps.

Stamp Location On Plans
Unspecified
Date On Stamps
Expiration Date

Fire setbacks

Fire Setback Enforced
1
Setback Notes

Standard

Structural & loads

Wind Speed
150
Wind Notes

Exposure Category C

Snow Load
30
Snow Load Notes

30 psf roof & 30 psf ground snow loads

Reducible Snow Load Allowed
0
Max Attachment Spacing
96
Structural Notes

### Engineer Requirements ### * An Engineer’s report regarding the dead-load capability of the existing roof structure and its ability to support the added weight of the solar photovoltaic system. The report must include the required wind speed and roof snow load for the site. If the panels project above the ridge line of the roof, this must also be part of the report. * Wind speed: 136 MPH (Vult) east of HWY 93. 150 MPH (Vult) west of HWY 93. Exposure C. * Roof snow load: 30 PSF * Ground snow load: 30 PSF

Minimum Ground On Roof
#6

Electrical

Electrical Load Calcs Required
Derates
Allowed POI
Load Side Taps,PV Breaker,Meter Adapter,Line Side Taps
Panel Schedule Required
Partial Home Backup
Temperature Rating
75
De Rating Ampacity
0.96

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

Standard

Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Plan set

Plan Set Requirements

NONE

Cover Page

Please include wind speed and roof snow load on front page of plans as well as in structural analysis.

Roof Plan

STANDARD

Electrical Diagram

Centerfed 120%: Not Sure Please provide information to assure interconnection method is compliant per 705.12(B). MPUs will required the installation of a surge protective device TAPS For line/load side tap, plans need to show #6 AWG GEC from fusible disconnect to grounding electrode ; and needs to be labeled as irreversibly crimped to existing GEC. Provide manufacturer specification sheets and installation guidelines for the wire connectors utilized for the supply side interconnection to assure compliance with 2020 NEC Section 230.46 Load taps: Provide size, property (copper or aluminum), insulation type of the feeders and the load being fed by the feeders (sub panel, gateway, etc.)

Ground mount

Ground Mount Fencing Required
No
Ground Mount Notes

Soil Class: Clay

Please Read GM process in LS to determine setbacks - Setbacks are dependent on Zoning.

Ground Mount Requires Soil Sample
Soil Study
Compiled from public records, 2026. Requirements change with code cycles and local amendments. Verify with the City of Arvada (CO) building department before you rely on this, and treat it as a research head start, not a ruling. Getting quotes? Run them through the quote checker first.