City of Littleton (CO)
Codes
- NEC Code Version
- 2023
- Code List
2024 International Building Code by the International Code Council, Inc. ("2024 IBC")
2024 International Energy Conservation Code by the International Code Council, Inc. ("2024 IECC")
2024 International Existing Building Code by the International Code Council, Inc. ("2024 IEBC")
2024 International Fuel Gas Code by the International Code Council, Inc. ("2024 IFGC")
2024 International Mechanical Code by the International Code Council, Inc. ("2024 IMC")
2024 International Plumbing Code by the International Code Council, Inc. ("2024 IPC")
2024 International Property Maintenance Code by the International Code Council, Inc. ("2024 IPMC")
2024 International Residential Code by the International Code Council, Inc. ("2024 IRC")
2024 International Swimming Pool and Spa Code by the International Code Council, Inc. ("2024 ISPSC")
2024 International Wildland-Urban Interface Code by the International Code Council, Inc. (“2024 IWUIC”)
ICC A117.1-2017 Standard with Supplement 1 - Accessible and Usable Buildings and Facilities by the International Code Council, Inc. (“2017 ICC A117.1”)
NFPA 70 National Electric Code 2023 Edition by the National Fire Protection Association ("2023 NEC")
1997 Uniform Code for the Abatement of Dangerous Buildings by the International Conference of Building Officials
Colorado Model Electric Ready and Solar Ready Code, by The Colorado Department of Local Affairs and Colorado Energy Office on June 1, 2023
2021 International Fire Code by the International Code Council, Inc. ("2021 IFC")
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- SolarAPP+ Status
- Targeted
- Any SolarAPP+ Restrictions
- 1
- SolarAPP+ Restrictions
- MPU,Derate
- How Many Plansets Required
- 1
- Revision Required
- 1
- Rough Inspection
- Rough Electrical
- New Planset Required For Module Swap
- 0
Stamps
- Ee Stamp Required On SLD
- Yes
- Wet Stamps Required
- Digital Structural,Digital Electrical
- Structural Calculations Required
- Yes
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 1
- Ridge Setback
- 3
- Rake Setback
- 3
- Hip Valley Setback
- 1
- Eave Setback
- 3
- Setback Notes
36 in required around all sides including ridge, rakes, and eaves.
1.5 Hip/Valley Setbacks
AHJ very strict
Structural & loads
- Wind Speed
- 136
- Wind Notes
Exposure Category C
Seismic Design Category B
- Snow Load
- 40
- Snow Load Notes
Ground Snow Load 40 PSF Non-Reducible
- Reducible Snow Load Allowed
- 0
- Max Attachment Spacing
- 96
- Structural Notes
Standard
- Minimum Ground On Roof
- #10
Electrical
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Line Side Taps,Meter Adapter,PV Breaker,Load Side Taps
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 1
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
Standard
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- No
Plan set
- Plan Set Requirements
EE stamp required on SLD.
- Attachment Detail
36 inches required around all sides including ridge, rakes, and eaves.
- Electrical Diagram
Centerfed 120%: Not Sure SLD needs to be stamped by electrical engineer. Reach out to staff electrical inspector for clarification on 120% rule for center-fed MSP's
- Custom Placards Required
- 0
- Non Standard Planset Requirements
- Single Line Diagram
Ground mount
- Ground Mount Fencing Required
- Mesh/Scrim