County of Jefferson (CO)
Codes
- NEC Code Version
- 2023
- Fire Code Version
- 2018 Building Code
- Code List
2018 INTERNATIONAL RESIDENTIAL CODE
2018 INTERNATIONAL BUILDING CODE
2018 INTERNATIONAL ENERGY CONSERVATION CODE
2018 INTERNATIONAL EXISTING BUILDING CODE
2018 INTERNATIONAL FUEL GAS CODE
2018 INTERNATIONAL MECHANICAL CODE
2018 INTERNATIONAL PLUMBING CODE
2023 NATIONAL ELECTRICAL CODE
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- SolarAPP+ Status
- Targeted
- Any SolarAPP+ Restrictions
- 1
- SolarAPP+ Restrictions
- MPU,Derate
- How Many Plansets Required
- 1
- Revision Required
- 1
- Rough Inspection
- Rough Electrical
- New Planset Required For Module Swap
- 1
Stamps
- Ee Stamp Required On SLD
- No
- Wet Stamps Required
- Digital Structural
- Structural Calculations Required
- Yes
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
Standard
Structural & loads
- Wind Speed
- 130
- Wind Notes
Exposure Category C
- Snow Load
- 999
- Snow Load Notes
* Find Roof snow load and Ground snow load requirements on Jefferson County Address Wizard. * Roof & ground snow load varies due to changes of Elevation and Location. Check on Jeff Co website for "Address Wizard": * The ground snow load is to be used as a baseline to determine roof snow load. The roof snow load should be separate on the calcs from roof live/dead loads.
Address Lookup - Address Search (jeffco.us)
Address Lookup | Jefferson County, CO (jeffco.us)
- Reducible Snow Load Allowed
- 0
- Max Attachment Spacing
- 96
- Structural Notes
SE digital stamps on corresponding PV pages & PE Letter / Calcs. Ground and roof snow loads required on structural calcs and letter. WS: 130 MPH GSN: Up to 72 LBS * Find Roof snow load and Ground snow load requirements on Jefferson County Address Wizard.
- Minimum Ground On Roof
- #6
Electrical
- Electrical Load Calcs Required
- Derates
- Allowed POI
- PV Breaker,Meter Adapter,Load Side Taps,Line Side Taps
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 1
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
No published information about battery placement. Mays, Jovan. AHJ: City of Lakewood (CO). Equipment in garage no longer required. [DCR 122820] Battery and inverter are supposed to be inside the garage. [DCR 083120] PM required for projects over 10kW-DC. Call out STEEL PRODUCTION METER, 120/240V 3-WIRE . Install a brass tag that says PV PROD and the house number but not the whole address. For example, if the address is 6200 West Mexico Avenue, the brass tag should say PV PROD 6200 .
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- No
Plan set
- Electrical Diagram
- Custom Placards Required
- 0
Ground mount
- Ground Mount Fencing Required
- No
- Ground Mount Notes
Soil Class: Clay
- Ground Mount Requires Soil Sample
- Soil Study
- Setback Front Yard
- 50
- Setback Back Yard
- 5
- Setback Side Yard
- 20