Town of Buena Vista (CO)

Colorado Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2017
Fire Setback Enforced0

Codes

NEC Code Version
2017
Code List

2015 INTERNATIONAL BUILDING CODE 2015 INTERNATIONAL FIRE CODE 2006 INTERNATIONAL ENERGY CONSERVATION CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

Revision Required
0
New Planset Required For Module Swap
0

Fire setbacks

Fire Setback Enforced
0
Setback Notes

Standard

Structural & loads

Wind Speed
120
Snow Load
999
Snow Load Notes

Snow loads are based on zones within the county. Please refer to the PDF "Snow Load Map" uploaded below to determine the snow load for the site. Snow load can be reduced, but not reduced below 35 psf.

Reducible Snow Load Allowed
1
Max Attachment Spacing
96
Minimum Ground On Roof
#10

Electrical

Electrical Load Calcs Required
Derates
Allowed POI
Load Side Taps,PV Breaker,Line Side Taps,Meter Adapter
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
0.96

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

Standard

Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Ground mount

Ground Mount Fencing Required
Mesh/Scrim