NEC Code Version2023
Wet Stamps RequiredDigital Structural

Codes

NEC Code Version
2023
Code List

2018 INTERNATIONAL BUILDING CODE

2018 INTERNATIONAL ENERGY CONSERVATION CODE

2018 INTERNATIONAL FIRE CODE

2018 INTERNATIONAL FUEL GAS CODE

2018 INTERNATIONAL MECHANICAL CODE

2018 INTERNATIONAL PLUMBING CODE

2018 INTERNATIONAL RESIDENTIAL CODE

2018 INTERNATIONAL SWIMMING POOL AND SPA CODE

2023 NATIONAL ELECTRICAL CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

Revision Required
No
Rough Inspection
None
New Planset Required For Module Swap
No

Stamps

Ee Stamp Required On SLD
No
Wet Stamps Required
Digital Structural
Structural Calculations Required
Yes
Stamp Location On Plans
Unspecified
Date On Stamps
Date Plans are Stamped

Structural & loads

Wind Speed
95
Snow Load
0
Reducible Snow Load Allowed
Yes
Structural Notes

Stamped structural calcs and stamps on plans.

Minimum Ground On Roof
#10

Ground mount

Ground Mount Fencing Required
Mesh/Scrim