Solar Sanity Checksolar, decoded Independent. Nothing you type leaves your browser.

City of Hailey (ID)

Idaho Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2017
Fire Code Version2018 Building Code
Wet Stamps RequiredDigital Structural

Codes

NEC Code Version
2017
Fire Code Version
2018 Building Code
Code List

2018 INTERNATIONAL BUILDING CODE 2018 INTERNATIONAL RESIDENTIAL CODE 2018 INTERNATIONAL FIRE CODE 2018 INTERNATIONAL ENERGY CONSERVATION CODE 2018 INTERNATIONAL EXISTING BUILDING CODE 2018 INTERNATIONAL FUEL GAS CODE 2018 INTERNATIONAL MECHANICAL CODE 2018 INTERNATIONAL PLUMBING CODE 2017 NATIONAL ELECTRICAL CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

Revision Required
1
New Planset Required For Module Swap
0

Stamps

Ee Stamp Required On SLD
No
Wet Stamps Required
Digital Structural
Structural Calculations Required
Yes

Fire setbacks

Setback Notes

Standard

Structural & loads

Wind Speed
115
Snow Load
120
Snow Load Notes

Ground Snow Load 120 lbs

Roof Snow Load 100 lbs

Reducible Snow Load Allowed
1
Structural Notes


Minimum Ground On Roof
#10

Electrical

Electrical Load Calcs Required
Derates
Allowed POI
Meter Adapter,Line Side Taps,PV Breaker,Load Side Taps
Service Ground Requirements

For new MBE (Main Breaker Enclosure): Two ground rods are to be driven with continuous EGC landing in MBE.

Temperature Rating
90
De Rating Ampacity
0.91

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

Standard

Plan set

Electrical Diagram

IT-POLARIS 350 service side rated are the ONLY city approved taps for LST.

Ground mount

Ground Mount Fencing Required
Mesh/Scrim
Compiled from public records, 2026. Requirements change with code cycles and local amendments. Verify with the City of Hailey (ID) building department before you rely on this, and treat it as a research head start, not a ruling. Getting quotes? Run them through the quote checker first.