Idaho Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2023
Wet Stamps RequiredNone

Codes

NEC Code Version
2023
Code List

2020 IDAHO RESIDENTIAL CODE

2020 IDAHO ENERGY CONSERVATION CODE

2018 INTERNATIONAL BUILDING CODE

2018 INTERNATIONAL EXISTING BUILDING CODE

2018 INTERNATIONAL FUEL GAS CODE

2018 INTERNATIONAL MECHANICAL CODE

2018 INTERNATIONAL FIRE CODE

2023 NATIONAL ELECTRICAL CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

Revision Required
0
New Planset Required For Module Swap
0

Stamps

Ee Stamp Required On SLD
No
Wet Stamps Required
None
Structural Calculations Required
No

Structural & loads

Reducible Snow Load Allowed
1
Max Attachment Spacing
96
Minimum Ground On Roof
#10

Electrical

AC Disconnect Required
No
Electrical Load Calcs Required
Derates
Temperature Rating
90
De Rating Ampacity
0.91

Plan set

Electrical Diagram
  • Electrical permit is through the State of Idaho (DOPL) (ID). Please see page for design requirements.

Ground mount

Ground Mount Fencing Required
No