City of Palos Heights (IL)

Illinois Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2014
Fire Code Version2015 Building Code
Wet Stamps RequiredDigital Structural

Codes

NEC Code Version
2014
Fire Code Version
2015 Building Code
Code List
2009 INTERNATIONAL BUILDING CODE 2009 INTERNATIONAL FUEL GAS CODE 2009 INTERNATIONAL PROPERTY MAINTENANCE CODE 2009 INTERNATIONAL RESIDENTIAL CODE 2014 ILLINOIS PLUMBING CODE 2015 INTERNATIONAL ENERGY CONSERVATION CODE 2011 CITY OF CHICAGO ELECTRICAL CODE
ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

How Many Plansets Required
1
Revision Required
0
New Planset Required For Module Swap
0

Stamps

Ee Stamp Required On SLD
No
Wet Stamps Required
Digital Structural
Structural Calculations Required
Yes
Stamp Location On Plans
Unspecified

Fire setbacks

Setback Notes
Standard

Structural & loads

Wind Speed
90
Snow Load
20
Reducible Snow Load Allowed
1
Minimum Ground On Roof
#10

Electrical

Allowed POI
Line Side Taps,Load Side Taps,PV Breaker,Meter Adapter
Temperature Rating
90
De Rating Ampacity
0.91

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes
Standard

Ground mount

Ground Mount Fencing Required
Mesh/Scrim