County of Rock Island (IL)
NEC Code Version2014
Fire Code Version2015 Building Code
Wet Stamps RequiredNone
Fire Setback Enforced1
Codes
- NEC Code Version
- 2014
- Fire Code Version
- 2015 Building Code
- Code List
2012 INTERNATIONAL BUILDING CODE
2012 INTERNATIONAL ENERGY CONSERVATION CODE
2012 INTERNATIONAL FIRE CODE
2012 INTERNATIONAL SOLAR ENERGY PROVISIONS AND ORDINANCE
2012 INTERNATIONAL RESIDENTIAL BUILDING CODE
2014 NATIONAL ELECTRICAL CODE
- IEBC Accepted
- 1
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- Revision Required
- 0
- Rough Inspection
- None
- New Planset Required For Module Swap
- 0
Stamps
- Ee Stamp Required On SLD
- No
- Wet Stamps Required
- None
- Structural Calculations Required
- No
Fire setbacks
- Fire Setback Enforced
- 1
Structural & loads
- Wind Speed
- 90
- Snow Load
- 20
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Minimum Ground On Roof
- #10
Electrical
- AC Disconnect Required
- No
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Meter Adapter,Line Side Taps,PV Breaker,Load Side Taps
- Temperature Rating
- 90
- De Rating Ampacity
- 0.91
- BOS Restrictions
Standard
Battery / ESS
- Unique Battery Placards Needed
- 0
- Separate ESS Disconnect Required
- No
- ESS Elevation Detail Required
- No
Plan set
- Plan Set Requirements
Standard
- Cover Page
Standard
- Site
Standard
- Roof Plan
Standard
- Attachment Detail
Standard
- Electrical Diagram
Standard
- Label Page
Standard
- Custom Placards Required
- 1
- Placards Notes
NEED CUSTOM SITE MAP PLACARD FOR MIDAMERICA UTILITY
Ground mount
- Ground Mount Fencing Required
- No
- Setback Front Yard
- 10
- Setback Back Yard
- 5
- Setback Side Yard
- 5