Village of Buffalo Grove (IL)
Codes
- NEC Code Version
- 2017
- Fire Code Version
- 2018 Building Code
- Code List
2018 INTERNATIONAL BUILDING CODE, AS AMENDED
2018 INTERNATIONAL RESIDENTIAL CODE, AS AMENDED
2018 INTERNATIONAL FIRE CODE, AS AMENDED
2017 NATIONAL ELECTRIC CODE, AS AMENDED
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- How Many Plansets Required
- 2
- Revision Required
- 1
- Rough Inspection
- Rough Electrical
- New Planset Required For Module Swap
- 0
Stamps
- Wet Stamps Required
- Digital Structural
- Structural Calculations Required
- Yes
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
Standard
Structural & loads
- Wind Speed
- 90
- Wind Notes
Exposure Category B
- Snow Load
- 30
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Structural Notes
Standard
- Minimum Ground On Roof
- #10
Electrical
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Meter Adapter,PV Breaker,Line Side Taps,Load Side Taps
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 1
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
Standard
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- No
Plan set
- Plan Set Requirements
AHJ was not aware of 2018 modified setbacks. Requested us to submit the portion of 2018 IRC that goes over modified setbacks if our plans are proposing them. (for the first submittal only) All equipment installed is required to have a larger short-circuit-current rating than the available fault current. Provide the cutsheets for all equipment and provide the short circuit current rating. Provide the cutsheets for all equipment, enclosures and grounding devices. Provide all installation instructions from Solaredge, including grounding requirements. IF supplyside connection is shown outside an enclosure, provide the exact location for this connection. If a junction box is used between the meter and the service panel, show this on the drawing.
- Electrical Diagram
MPU
- SLD REQUIRED
- CALL OUT EXISITNG SERVICE SIZE , SIZE OF FEEDERS , LOCATION OF ELECTRICAL PANEL
- LOAD CALCULATIONS REQUIRED
- EXAMPLE ----> EXAMPLE
- Electrical Diagram Notes
At the AC PV disconnect switch, a grounding electrode system is required to be installed. The grounding electrode conductor is required to be installed continuously and unbroken from this switch to the street side of the water meter. EMT conduit is required.
- Custom Placards Required
- 0
Ground mount
- Ground Mount Fencing Required
- Mesh/Scrim