City of Haverhill (MA)

Massachusetts Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2023
Fire Code Version2018 Building Code
Wet Stamps RequiredDigital Structural
Fire Setback Enforced1

Codes

NEC Code Version
2023
Fire Code Version
2018 Building Code
Code List

10TH EDITION OF THE MA STATE BUILDING CODE 780

2021 INTERNATIONAL BUILDING CODE W/780 CMR

2021 INTERNATIONAL RESIDENTIAL CODE W/780 CMR

2021 INTERNATIONAL EXISTING BUILDING CODE

2021 INTERNATIONAL MECHANICAL CODE

2021 INTERNATIONAL ENERGY CONSERVATION CODE

2021 INTERNATIONAL FIRE CODE

2023 NATIONAL ELECTRICAL CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

How Many Plansets Required
Other (See Submission Notes)
Revision Required
0
New Planset Required For Module Swap
0

Stamps

Ee Stamp Required On SLD
No
Wet Stamps Required
Digital Structural
Structural Calculations Required
Yes
Ee Stamp Notes
No EE required
Stamp Location On Plans
Unspecified
Date On Stamps
Expiration Date

Fire setbacks

Fire Setback Enforced
1
Setback Notes

The Haverhill Fire Department requests that roof mounted solar arrays are installed with the following setbacks:

Gable roof: not less than two 3 foot wide access pathways from the eave to the ridge on each roof slope where solar panels are located.

  • One access pathway shall be provided on the street or driveway side of the roof
  • No Overhead Electrical crossing access pathways
  • NO conduit across access pathways.
  • No overgrown trees or shrubs below access pathways.

Setbacks at ridge (Both Sides):

  • 18โ€ if PV coverage < 33%
  • (If sprinkled < 66%)
  • 36โ€ if PV coverage >33%
  • (If sprinkled > 66%)

Hip roof: one 3-foot-wide access pathway from the eave to the ridge on each roof slope where panels are located

Hip/valley: 18โ€ wide access pathway from the eave to the ridge


ESS to follow NFPA 855 2023 ed. If applicable


Fire set backs for flat roofs

Due to the fact that there is no current set back wording in NFPA 1 on residential flat roofs The Haverhill Fire Department requests that FLAT ROOF mounted solar arrays are installed with the following setbacks:

  • Around the perimeter of the roof at least an 18โ€ set back. 
  • One 36โ€ access pathway shall be provided on the street or driveway side of the roof running across the roof from EAVE to EAVE.
  • From EAVE to EAVE in the opposite direction a minimum 18โ€ escape pathway running at the center of the roof forming a + pattern. This allows firefighter escape points at all Eave lines
  • No Overhead Electrical crossing access pathways
  • NO conduit across access pathways.
  • No overgrown trees or shrubs below access pathways.
  • ESS to follow NFPA 855    2023 ed.     If applicable

Structural & loads

Wind Speed
120
Wind Notes

Exposure Category B

Snow Load
50
Reducible Snow Load Allowed
1
Max Attachment Spacing
96
Structural Notes

Standard

Minimum Ground On Roof
#10

Electrical

Electrical Load Calcs Required
Derates
Allowed POI
PV Breaker,Load Side Taps,Line Side Taps,Meter Adapter
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
1

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

No battery can be placed in the basement

If Basement is the only please please reach out to BM for review

Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Plan set

Roof Plan

-Conduit will need to be run internally or in ways that would avoid crossing the fire pathways.

Attachment Detail

Gable Roof: Not less than two 3 foot wide access pathways from the eave to the ridge on each roof slope where panels are located One access pathway shall be on the street or driveway side of the roof If solar panels are to be installed on two sides of a roof, panels shall be location no higher than 3 feet below the ridge on one side to allow for the ventilation of smoke in the event of a fire. The other side of the roof the panels shall be located no higher than 18 inches below the ridge. Hip Roof: On 3 foot wide access pathway from the eave to the ridge on each roof slope where panels are located Hip/Valley: 18 inch wide access pathway from the eave to the ridge

Custom Placards Required
0

Ground mount

Ground Mount Fencing Required
Mesh/Scrim
Ground Mount Notes

System > 10kW

  • Front - 100'
  • Side - 75" ( lot abuts a residential district - 100')
  • Back - 75' ( lot abuts a residential district - 100')
Compiled from public records, 2026. Requirements change with code cycles and local amendments. Verify with the City of Haverhill (MA) building department before you rely on this, and treat it as a research head start, not a ruling. Getting quotes? Run them through the quote checker first.