Town of Uxbridge (MA)
NEC Code Version2023
Fire Code Version2018 Building Code
Wet Stamps RequiredDigital Structural,Digital Electrical
Fire Setback Enforced1
Codes
- NEC Code Version
- 2023
- Fire Code Version
- 2018 Building Code
- Code List
10TH EDITION OF THE MA STATE BUILDING CODE 780
2021 INTERNATIONAL BUILDING CODE W/780 CMR
2021 INTERNATIONAL RESIDENTIAL CODE W/780 CMR
2021 INTERNATIONAL EXISTING BUILDING CODE
2021 INTERNATIONAL MECHANICAL CODE
2021 INTERNATIONAL ENERGY CONSERVATION CODE
2021 INTERNATIONAL FIRE CODE
2023 NATIONAL ELECTRICAL CODE
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- How Many Plansets Required
- 2
- Revision Required
- 0
- Rough Inspection
- None
- New Planset Required For Module Swap
- 0
Stamps
- Ee Stamp Required On SLD
- Yes
- Wet Stamps Required
- Digital Structural,Digital Electrical
- Structural Calculations Required
- Yes
- Ee Stamp Notes
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
Standard
Structural & loads
- Wind Speed
- 128
- Wind Notes
Exposure Category B
- Snow Load
- 40
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Structural Notes
AHJ requires Initial Construction Affidavit and Final Construction Affidavit from the files section below to be completed and stamped by both the structural and electrical engineer for each project.
- Minimum Ground On Roof
- #10
Electrical
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Line Side Taps,Load Side Taps,PV Breaker,Meter Adapter
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 0.96
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
Standard
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- No
Plan set
- Custom Placards Required
- 0
Ground mount
- Ground Mount Fencing Required
- Mesh/Scrim
- Ground Mount Notes
75' from all street sides
- Setback Front Yard
- 75