City of Troy (MI)
NEC Code Version2023
Fire Code Version2015 Building Code
Wet Stamps RequiredDigital Structural
Fire Setback Enforced1
Codes
- NEC Code Version
- 2023
- Fire Code Version
- 2015 Building Code
- Code List
2021 MICHIGAN BUILDING CODE
2015 MICHIGAN RESIDENTIAL CODE
2021 MICHIGAN REHABILITATION CODE
2021 MICHIGAN MECHANICAL CODE
2021 MICHIGAN RESIDENTIAL ENERGY CODE
2015 MICHIGAN ENERGY CODE
2023 NATIONAL ELECTRICAL CODE
2023 MICHIGAN ELECTRICAL CODE
- IEBC Accepted
- 1
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- Revision Required
- 1
- Rough Inspection
- None
- New Planset Required For Module Swap
- 0
Stamps
- Ee Stamp Required On SLD
- No
- Wet Stamps Required
- Digital Structural
- Structural Calculations Required
- Yes
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- N/A
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
2015 FSB enforced: Always have 3-foot-wide access pathways from the eave to the ridge on each roof slope where panels or modules are located.
Structural & loads
- Wind Speed
- 115
- Wind Notes
https://ascehazardtool.org/
- Snow Load
- 25
- Snow Load Notes
https://ascehazardtool.org/
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Minimum Ground On Roof
- #10
Electrical
- AC Disconnect Required
- Yes
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Meter Adapter,PV Breaker,Line Side Taps,Load Side Taps
- Panel Schedule Required
- Partial Home Backup
- Supply Tap Neutral Ground Bond Required
- 1
- Temperature Rating
- 90
- De Rating Ampacity
- 0.91
- BOS Restrictions
Standard
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
- INTERIOR BATTERY MOUNT REQUIRE SMOKE DETECTOR
- Separate ESS Disconnect Required
- No
- ESS Elevation Detail Required
- No
Plan set
- Plan Set Requirements
- Cover Page
- Cover Page Notes
- Site
- Roof Plan
- Attachment Detail
- Electrical Diagram
Grounding
- Ground rod must be shown on the right side of the disconnect.
- Neutral wire should remain continuous - do not cut or bond inside the disconnect.
- Neutral-to-ground bond must occur only at the first means of disconnect (typically the Main Service Panel (MSP)).
- Reflect the utility grounding bond connection in the main service panel.
Tap Configuration (LST)
- All taps must be located outside and in a tap box near the Utility Meter.
- All taps must be accompanied with a fused disconnect within 5' of the Utility Meter.
- BOND N-G
Conductor Terminations
- Clearly show conductor termination points - not just symbolic boxes (The wires must attach to the disconnect switch, breaker, etc.. It cannot "end at the disconnect box outline).
- Ensure all wires are shown landing in terminals and disconnects accurately.
MPU/Battery
- Fused disconnect between MID and UM
- Surge protection required
PROVIDE UL LISTED EQUIPMENT FOR POI
- Label Page
- Custom Placards Required
- 0
Ground mount
- Ground Mount Fencing Required
- No
- Ground Mount Notes
Standard Ground Mount requirements
- Setback Front Yard
- 10
- Setback Back Yard
- 5
- Setback Side Yard
- 5