Town of Durham (NH)

New Hampshire Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2020
SolarAPP+ StatusTargeted
Wet Stamps RequiredDigital Structural
Fire Setback Enforced1

Codes

NEC Code Version
2020
Code List

2021 NH STATE BUILDING CODE

2021 NH STATE FIRE CODE

2021 INTERNATIONAL BUILDING CODE

2021 INTERNATIONAL RESIDENTIAL CODE

2021 INTERNATIONAL MECHANICAL CODE

2021 INTERNATIONAL PLUMBING CODE

2018 INTERNATIONAL ENERGY CONSERVATION CODE

2021 INTERNATIONAL EXISTING BUILDING CODE

2021 INTERNATIONAL SWIMMING POOL AND SPA CODE

2021 NFPA 1, FIRE CODE AS AMENDED BY SAF-FMO 300

2021 NFPA 101 LIFE SAFETY CODE AS AMENDED BY SAF-FMO 300

2020 NATIONAL ELECTRICAL CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

SolarAPP+ Status
Targeted
Any SolarAPP+ Restrictions
1
SolarAPP+ Restrictions
MPU,Derate
How Many Plansets Required
2
Revision Required
0
Rough Inspection
None
New Planset Required For Module Swap
0

Stamps

Wet Stamps Required
Digital Structural
Structural Calculations Required
Yes
Stamp Location On Plans
Unspecified
Date On Stamps
Expiration Date

Fire setbacks

Fire Setback Enforced
1
Setback Notes

18" setbacks if covering less than 50% of the roof. 36" setbacks if covering more than 50%.

Structural & loads

Wind Speed
120
Wind Notes

Exposure Category B

Snow Load
60
Reducible Snow Load Allowed
1
Max Attachment Spacing
96
Structural Notes

SE digital stamps on corresponding PV Pages. The structural letter must reference that the panel install will comply with the placement in the NH amendments: "Photovoltaic systems installed in one- and two-family dwellings and townhouses shall be in accordance with NFPA 1 Section 11.12.2.2.2. Exception: Photovoltaic systems not occupying more than 50% of the aggregate roof area of one- and two-family dwellings only. When applying this exception a minimum 18โ€ ridge setback shall be required unless approved by the AHJ."

Minimum Ground On Roof
#10

Electrical

Electrical Load Calcs Required
Derates
Allowed POI
Line Side Taps,PV Breaker,Load Side Taps,Meter Adapter
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
0.91

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

Standard

Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Ground mount

Ground Mount Fencing Required
Mesh/Scrim
Compiled from public records, 2026. Requirements change with code cycles and local amendments. Verify with the Town of Durham (NH) building department before you rely on this, and treat it as a research head start, not a ruling. Getting quotes? Run them through the quote checker first.