Township of Washington (Morris County) (NJ)

New Jersey Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2020
Fire Code Version2018 Building Code
Wet Stamps RequiredWet Structural
Fire Setback Enforced1

Codes

NEC Code Version
2020
Fire Code Version
2018 Building Code
Code List

2021 INTERNATIONAL BUILDING CODE

2021 INTERNATIONAL RESIDENTIAL CODE

2021 INTERNATIONAL FIRE CODE

2021 INTERNATIONAL ENERGY CONSERVATION CODE

2021 INTERNATIONAL EXISTING BUILDING CODE

2021 INTERNATIONAL FUEL GAS CODE

2021 INTERNATIONAL MECHANICAL CODE

2021 INTERNATIONAL PLUMBING CODE

2020 NATIONAL ELECTRICAL CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

How Many Plansets Required
3
Revision Required
0
Rough Inspection
None
New Planset Required For Module Swap
0

Stamps

Ee Stamp Required On SLD
No
Wet Stamps Required
Wet Structural
Structural Calculations Required
Yes
Stamp Location On Plans
Unspecified
Date On Stamps
Expiration Date

Fire setbacks

Fire Setback Enforced
1
Setback Notes

Standard

Structural & loads

Wind Speed
115
Snow Load
30
Reducible Snow Load Allowed
1
Max Attachment Spacing
96
Structural Notes

Standard

Minimum Ground On Roof
#10

Electrical

Electrical Load Calcs Required
Derates
Allowed POI
Load Side Taps,Meter Adapter,Line Side Taps,PV Breaker
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
0.91

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

State which appliance (including air conditioners) that is connected to the battery has the largest load.

Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Plan set

Electrical Diagram

If lineside tap (LST), then a Hoffman Tap Box (junction box) is required.

Electrical Diagram Notes


Custom Placards Required
0

Ground mount

Ground Mount Fencing Required
Mesh/Scrim
Ground Mount Notes

Ground Mount Design Requirements

  • Impervious Surface Schedule - Required for all ground mount jobs. Show all surfaces that block stormwater absorption (buildings, pavement, walkways, patios, gravel, decks, etc.).
  • NJDEP Requirements - If NJDEP applies, a signed and notarized ā€œRegulation Areas Release/Indemnificationā€ is required. (Confirm foundation type if concrete is restricted.)
  • Zoning Submission - Provide a property survey that shows: Setbacks, Lot coverage, Height of solar panels
  • Required buffer: continuous single row of evergreen landscaping, 6 ft tall at planting, around array and equipment.

Array Rules

  • Max height: 5 ft.
  • Evergreen buffer required (6 ft at planting, zoning officer approval).
  • Cannot occupy minimum side yard setback of principal structure.
  • Individual solar-powered light fixtures with their own panel are allowed without a zoning permit.

Definitions (to help with survey + zoning):

  • Impervious Surface - Any structure/surface preventing stormwater absorption (e.g., concrete, gravel, stone, decks, patios, pavers, roads, etc.).
  • Improved Lot Coverage - Any area of a lot covered by impervious surfaces (buildings, driveways, sidewalks, pools, patios, etc.).


Compiled from public records, 2026. Requirements change with code cycles and local amendments. Verify with the Township of Washington (Morris County) (NJ) building department before you rely on this, and treat it as a research head start, not a ruling. Getting quotes? Run them through the quote checker first.