County of Scioto (OH)
NEC Code Version2023
Wet Stamps RequiredNone
Fire Setback Enforced0
Codes
- NEC Code Version
- 2023
- Code List
2024 OHIO BUILDING CODE (2021 IBC)
2019 RESIDENTIAL CODE OF OHIO (2018 IRC)
2024 OHIO EXISTING BUILDING CODE (2021 IEBC)
2023 OHIO ELECTRIC CODE (2023 NFPA 70)
2021 INTERNATIONAL FIRE CODE (IFC)
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- Any SolarAPP+ Restrictions
- 0
- Revision Required
- 0
- New Planset Required For Module Swap
- 0
Stamps
- Ee Stamp Required On SLD
- No
- Wet Stamps Required
- None
- Structural Calculations Required
- No
Fire setbacks
- Fire Setback Enforced
- 0
- Setback Notes
Standard
Structural & loads
- Wind Speed
- 90
- Snow Load
- 20
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Minimum Ground On Roof
- #10
Electrical
- AC Disconnect Required
- No
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Load Side Taps,PV Breaker,Line Side Taps
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 0.91
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
Standard
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- No
Plan set
- Electrical Diagram
* Projects that have a SolarEdge inverter do NOT require a J-Box * Method of tie-in must be in the main service panel and cannot be in an exterior junction box. * We can tap, but it must be in the main panel * This is due to utility requirements. Not the AHJ. * The AHJ does not require a permit, but the utility will not accept LST without an AHJ inspection, and since this AHJ does not require permits, it is difficult to get an inspection.
Ground mount
- Ground Mount Fencing Required
- Mesh/Scrim