City of Beaverton (OR)
Codes
- NEC Code Version
- 2023
- Code List
2023 OREGON RESIDENTIAL SPECIALTY CODE
2022 OREGON STRUCTURAL SPECIALTY CODE
2022 OREGON MECHANICAL SPECIALTY CODE
2023 OREGON PLUMBING SPECIALTY CODE
2025 OREGON ENERGY EFFICIENCY SPECIALTY CODE
2010 OREGON MANUFACTURED DWELLING INSTALLATION SPECIALTY CODE
2023 National Electrical Code
- IEBC Accepted
- 1
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- How Many Plansets Required
- 1
- Revision Required
- 1
- New Planset Required For Module Swap
- 1
Stamps
- Ee Stamp Required On SLD
- No
- Wet Stamps Required
- Digital Structural
- Structural Calculations Required
- Yes
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
All solar roof planes MUST have 36โ pathways along 3 sides of the roof plane. Pathways cannot be over unsupported areas like overhangs and eaves. The following exceptions below allow us to avoid having 3 pathways on each plane:
- Total array area is not greater than 1,000 sqft and it has an intersecting adjacent roof plane free of solar panels. 1. If #1 applies AND total array area does not exceed 25% of total roof area, then one 12โ pathway is required along each side of the horizontal ridge. 2. If #1 applies AND the total array area exceeds 25% of total roof area, then one 12โ pathway is required song each side of the horizontal ridge AND one 36โ pathway from ridge to eave shall be provided.
- Pathways are not required on non-occupied accessory structures, provided that they are separated from occupied structures by not less than 60 inches or by a minimum two-hour fire-rated assembly. When using this exception, please include a dimension of the shortest distance between the array building and the nearest occupied structure.
Pathways are not allowed within 12" of low point valleys.
Additional information and examples of acceptable fire setbacks can be found in the files below.
Structural & loads
- Wind Speed
- 97
- Snow Load
- 25
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 48
- Structural Notes
* For Roof Mounts- See Prescriptive Path Checklist attached. If meeting PPC criteria, the a structural stamp will not be needed. If not used, SE will be required per AHJ
- Minimum Ground On Roof
- #10
Electrical
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Load Side Taps,Line Side Taps,Meter Adapter,PV Breaker
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 0.91
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
Standard
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- No
Plan set
- Plan Set Requirements
* Module spec sheet should show UL listing * For Roof Mounts- See Prescriptive Path Checklist attached. If meeting PPC criteria, the a structural stamp will not be needed. If not used, SE will be required per AHJ
- Attachment Detail
Max 4' attachment span per Oregon State code
Ground mount
- Ground Mount Fencing Required
- Mesh/Scrim