City of Brigham (UT)

Utah Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2017
Fire Code Version2018 Building Code
Wet Stamps RequiredDigital Structural
Fire Setback Enforced1

Codes

NEC Code Version
2017
Fire Code Version
2018 Building Code
Code List

2021 INTERNATIONAL BUILDING CODE 2021 INTERNATIONAL RESIDENTIAL CODE 2021 INTERNATIONAL MECHANICAL CODE 2021 INTERNATIONAL PLUMBING CODE 2021 INTERNATIONAL FUEL GAS CODE 2021 INTERNATIONAL ENERGY CONSERVATION CODE 2021 INTERNATIONAL EXISTING BUILDING CODE 2021 INTERNATIONAL SWIMMING POOL AND SPA CODE 2020 NATIONAL ELECTRICAL CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

How Many Plansets Required
1
Revision Required
0
New Planset Required For Module Swap
0

Stamps

Wet Stamps Required
Digital Structural
Structural Calculations Required
Yes
Stamp Location On Plans
Unspecified
Date On Stamps
Expiration Date

Fire setbacks

Fire Setback Enforced
1
Setback Notes

Standard

Structural & loads

Wind Speed
115
Wind Notes

Exposure Category C

Snow Load
43
Reducible Snow Load Allowed
1
Max Attachment Spacing
96
Structural Notes

#### **SNOW:** **Base ground load: 43 PSF** The ground snow load must be calculated in accordance with Section 1608.1.2 of the Utah Amended Code (Item 43) with regional snow load factors compliant with Table 1608.1.2(a). ** WIND: ** **Speed: 90 mph with 120 MPH 3 second wind gust. ** **Typical Exposure: “C” ** ** SEISMIC:** **Ground Motions: For specific acceleration values see the USGS National Seismic Hazard Maps.** Seismic Design Category: Site specific (per IBC 1613.3.5.1 Table 1613.3.5 (1)). "D" is typical **IBC: 2015** **IRC: 2015** **IECC: 2015** ** ** **ENGINEERING STAMP** **Plans must be wet stamped and signed by the engineer, copies may be denied. The engineering must be site specific.**

Minimum Ground On Roof
#10

Electrical

Electrical Load Calcs Required
Derates
Allowed POI
PV Breaker,Load Side Taps,Line Side Taps,Meter Adapter
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
0.91

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

Standard

Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Plan set

Plan Set Requirements

Utah does not want single panel arrays with railless systems. Please have layout changed if this happens

Attachment Detail

No single panel arrays with railless systems

Electrical Diagram

MPU

  • Clearly specify on the line diagram the exact model number of the service panel you are going to install and provide manufacturer specification sheets
  • The line diagram must be drawn correctly based on the type of new service panel that will be installed.
  • New service panel MUST be a type with only ONE MAIN breaker that shuts off all other breakers.
  • The new service panel CANNOT be a type which has additional breaker slots fed directly from the utility meter (i.e., cannot install a “hot bus” service panel per the 2020 NEC)
Label Page


Label Page Notes

All Jobs [A sign with the exact wording “Rapid Shutdown Switch for Solar PV System” will be provided next to the rapid shutdown disconnect for this system]

Custom Placards Required
0
Non Standard Planset Requirements
Single Line Diagram

Ground mount

Ground Mount Fencing Required
Mesh/Scrim