City of Layton (UT)

Utah Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2020
Fire Code Version2018 Building Code
Wet Stamps RequiredDigital Structural
Fire Setback Enforced1

Codes

NEC Code Version
2020
Fire Code Version
2018 Building Code
Code List

2021 INTERNATIONAL BUILDING CODE, (INCLUDING APPENDIX C & J) 2021 INTERNATIONAL RESIDENTIAL CODE (INCLUDING APPENDIX AQ and AE) 2021 INTERNATIONAL PLUMBING CODE 2021 INTERNATIONAL MECHANICAL CODE 2021 INTERNATIONAL FUEL GAS CODE 2021 INTERNATIONAL FIRE CODE 2020 NATIONAL ELECTRICAL CODE 2015 INTERNATIONAL ENERGY CONSERVATION CODE RESIDENTIAL PROVISIONS 2021 INTERNATIONAL ENERGY CONSERVATION CODE COMMERCIAL PROVISIONS 2021 INTERNATIONAL EXISTING BUILDING CODE 2015 INTERNATIONAL RESIDENTIAL CODE CHAPTER 11, ENERGY EFFICIENCY

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

How Many Plansets Required
1
Revision Required
1
New Planset Required For Module Swap
0

Stamps

Wet Stamps Required
Digital Structural
Structural Calculations Required
Yes
Stamp Location On Plans
Unspecified
Date On Stamps
Expiration Date

Fire setbacks

Fire Setback Enforced
1
Setback Notes

Fire Clearances for R-3 Roofs: Minimum 18” at ridge lines with loading on opposite slope (0” clearance if no panels on opposite slope); 18” at hips and valleys (0” clearance if no panels on opposite slope), 3’ at gables and rakes (must have at least two (2) three-foot (3’) pathways on opposite ends of single-ridge roofs); 0” clearance at soffits. 02/05/20 - Above clearances are NOT confirmed with the AHJ. Per Plan Checker Jayce, the AHJ follows IRC 2015 for fire clearances. When I read him the above data, he did not recognize the verbage and stated that the City prefers more restrictive fire clearances in the 2015 code. Recommend layouts follow standard IRC 2015 setbacks and clearances until confirmed. [JAM]

Structural & loads

Wind Speed
115
Wind Notes

Exposure Category C

Snow Load
30
Snow Load Notes

https://utahsnowload.usu.edu/

Reducible Snow Load Allowed
1
Max Attachment Spacing
96
Structural Notes

STRUCTURAL ENGINEER’S REPORT: Engineer’s report providing structural analysis of the existing roof system and its ability to handle the additional load, etc. 11/17/20 - "Utah does not want single panel arrays with railless systems. Please have layout changed if this happens" example photo below" - NH, per staff

Minimum Ground On Roof
#10

Electrical

Electrical Load Calcs Required
Derates
Allowed POI
PV Breaker,Meter Adapter,Line Side Taps,Load Side Taps
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
0.96

Battery / ESS

Unique Battery Placards Needed
1
ESS Notes

Battery systems require a dedicated AC Disconnect located within 10 ft of the UM. Battery Disconnect must bear this engraved label: BATTERY DISCONNECT . No published information about battery placement.

Separate ESS Disconnect Required
Local Disconnect
ESS Elevation Detail Required
No

Plan set

Plan Set Requirements

LG Chem Jobs: Please add the Storedge 25A Breaker image to plans for inspection, also remove the 25A breaker from the BLP Utah does not want single panel arrays with railless systems. Please have layout changed if this happens

Custom Placards Required
1

Ground mount

Ground Mount Fencing Required
Mesh/Scrim
Compiled from public records, 2026. Requirements change with code cycles and local amendments. Verify with the City of Layton (UT) building department before you rely on this, and treat it as a research head start, not a ruling. Getting quotes? Run them through the quote checker first.