City of North Ogden (UT)
Codes
- NEC Code Version
- 2020
- Fire Code Version
- 2018 Building Code
- Code List
2021 INTERNATIONAL BUILDING CODE 2021 INTERNATIONAL RESIDENTIAL CODE 2021 ENERGY CONSERVATION CODE 2021 INTERNATIONAL PLUMBING CODE 2021 INTERNATIONAL MECHANICAL CODE 2021 INTERNATIONAL FUEL GAS CODE 2020 NATIONAL ELECTRICAL CODE 2021 INTERNATIONAL FIRE CODE
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- SolarAPP+ Status
- Targeted
- Any SolarAPP+ Restrictions
- 1
- SolarAPP+ Restrictions
- MPU,Derate
- How Many Plansets Required
- 2
- Revision Required
- 0
- Rough Inspection
- None
- New Planset Required For Module Swap
- 0
Stamps
- Ee Stamp Required On SLD
- Yes - MSP 200A+
- Wet Stamps Required
- Digital Structural
- Structural Calculations Required
- Yes
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
Standard
Structural & loads
- Wind Speed
- 115
- Wind Notes
Exposure Category C
- Snow Load
- 999
- Snow Load Notes
above 5000 ft snow load min. is 43lbs
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Structural Notes
Standard
- Minimum Ground On Roof
- #10
Electrical
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Meter Adapter,PV Breaker,Line Side Taps,Load Side Taps
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 0.91
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
Standard
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- No
Plan set
- Plan Set Requirements
Utah does not want single panel arrays with railless systems. Please have layout changed if this happens Provide photos of the existing service panelboard and photos of its interior labels. Photos must be with the service panelboard's front covers open and show the ratings of all breakers therein. The photos of labels must also clearly show the rating of the panelboard. In addition to the above noted comment, if the utility meter base is not part of the same panelboard as the service panelboard, please also provide photos of the meter base and the service conduit (with photos taken from about 5 to 10 feet away from the equipment).
- Attachment Detail
No single panel arrays
- Electrical Diagram
Please be aware that the line diagram must be drawn correctly based on the type of service panel that this home has. In other words, the layout of the service panel on the diagram must match that of the actual service panel. Generic layouts of service panels on the line diagram will not be accepted.
- Label Page
## BATTERY Please update the signage sheet to include a sign with the exact wording. “ENERGY STORAGE SYSTEM DISCONNECT.” The sign must include the Nominal AC Voltage and Maximum DC voltage of the ESS system (NEC 706.15(C)). On the signage sheet, please add a sign to be placed at the service entrance that identifies the battery chemistry included in the ESS. IRC R327.11 (2021 Utah Amendments)
- Custom Placards Required
- 0
Ground mount
- Ground Mount Fencing Required
- Mesh/Scrim