City of Washington City (UT)
NEC Code Version2020
Fire Code Version2018 Building Code
Wet Stamps RequiredDigital Structural
Fire Setback Enforced1
Codes
- NEC Code Version
- 2020
- Fire Code Version
- 2018 Building Code
- Code List
2021 INTERNATIONAL BUILDING CODE
2021 INTERNATIONAL RESIDENTIAL CODE
2021 INTERNATIONAL MECHANICAL CODE
2021 INTERNATIONAL PLUMBING CODE
2021 INTERNATIONAL FUEL GAS CODE
2021 INTERNATIONAL ENERGY CONSERVATION CODE
2021 INTERNATIONAL EXISTING BUILDING CODE
2021 INTERNATIONAL SWIMMING POOL AND SPA CODE
2020 NATIONAL ELECTRICAL CODE
- IEBC Accepted
- 1
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- How Many Plansets Required
- 1
- Revision Required
- 1
- New Planset Required For Module Swap
- 0
Stamps
- Ee Stamp Required On SLD
- No
- Wet Stamps Required
- Digital Structural
- Structural Calculations Required
- Yes
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
Standard
Structural & loads
- Wind Speed
- 115
- Wind Notes
Exposure Category C
- Snow Load
- 21
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Minimum Ground On Roof
- #10
Electrical
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Line Side Taps,Load Side Taps,PV Breaker,Meter Adapter
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 75
- De Rating Ampacity
- 0.91
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
- ESS Disconnect required near meter
- Remote ESS Disconnect required Indicate how the Gateway isolates from the grid during an outage. (Need to provide a physical open)
- Heat/Smoke Detector required if battery is installed in garage.
- Indicate which loads are being transferred, if applicable
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- No
Plan set
- Plan Set Requirements
- Include photos of the existing electrical system, even if it's an MPU. IE: wire sizes, service panels, breaker info, etc.
- MPU projects: provide a spec sheet for the new panel and add the exact model number to line diagram (layout of new MSP must match, for example top fed must show main breaker at top etc)
- Electrical Diagram Notes
- If the service panel contains sub-panel fed by the feed-through lugs, NEC 705.12(B)(3)(3) [sum of handle rule] cannot be used for interconnection of the solar PV system.
- Custom Placards Required
- 0
- Non Standard Revision Requirements
- Cloud and label all changes clearly
Ground mount
- Ground Mount Fencing Required
- Mesh/Scrim