Utah Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2020
Fire Code Version2018 Building Code
Wet Stamps RequiredNone
Fire Setback Enforced1

Codes

NEC Code Version
2020
Fire Code Version
2018 Building Code
Code List

2021 INTERNATIONAL BUILDING CODE 2021 RESIDENTIAL BUILDING CODE 2021 INTERNATIONAL PLUMBING CODE 2021 INTERNATIONAL MECHANICAL CODE 2021 INTERNATIONAL FUEL GAS CODE 2021 INTERNATIONAL ENERGY CONSERVATION CODE 2021 INTERNATIONAL EXISTING BUILDING CODE 2021 INTERNATIONAL FIRE CODE 2020 NATIONAL ELECTRICAL CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

How Many Plansets Required
1
Revision Required
0
New Planset Required For Module Swap
0

Stamps

Wet Stamps Required
None
Structural Calculations Required
No
Stamp Location On Plans
Unspecified
Date On Stamps
Expiration Date

Fire setbacks

Fire Setback Enforced
1
Setback Notes
Standard

Structural & loads

Wind Speed
90
Wind Notes

Exposure Category B

Snow Load
45
Reducible Snow Load Allowed
1
Max Attachment Spacing
96
Structural Notes
We have a project that went through on a detached structure with no structural engineering. Sherman Sue I am pushing a project without Engineering and will monitor this one and update notes. Structural Engineering may only be required for Mobile Homes.
Minimum Ground On Roof
#8

Electrical

Electrical Load Calcs Required
Derates
Allowed POI
PV Breaker,Line Side Taps,Load Side Taps,Meter Adapter
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
0.96

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes
Standard
Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Plan set

Custom Placards Required
0

Ground mount

Ground Mount Fencing Required
Mesh/Scrim