City of Tumwater (WA)
NEC Code Version2023
Fire Code Version2018 Building Code
Fire Setback Enforced1
Codes
- NEC Code Version
- 2023
- Fire Code Version
- 2018 Building Code
- Code List
2021 INTERNATIONAL BUILDING CODE
2021 INTERNATIONAL RESIDENTIAL CODE
2021 INTERNATIONAL FIRE CODE
2021 INTERNATIONAL ENERGY CONSERVATION CODE
2021 INTERNATIONAL EXISTING BUILDING CODE
2021 INTERNATIONAL FUEL GAS CODE
2021 INTERNATIONAL MECHANICAL CODE
2021 INTERNATIONAL PLUMBING CODE
2023 NATIONAL ELECTRICAL CODE
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- Revision Required
- 0
- New Planset Required For Module Swap
- 0
Fire setbacks
- Fire Setback Enforced
- 1
Structural & loads
- Wind Speed
- 97
- Snow Load
- 25
- Snow Load Notes
https://hazards.atcouncil.org/#/
- Reducible Snow Load Allowed
- 1
Electrical
- Allowed POI
- Meter Adapter,Line Side Taps,PV Breaker,Load Side Taps
- Supply Tap Neutral Ground Bond Required
- 1
Plan set
- Plan Set Requirements
Additional electrical permit required through the State of Washington - Labor & Industries (WA). Please see page for requirements.
For all Trenches
- 2 Disconnects required - one at each end of trench
- Required for AC or DC trenches
- Electrical Diagram
For all Line Side Connections:
- Neutral and ground bonded in fused disconnect
- #6 bare copper run from N/G bar to (E) MSP's GEC and crimped
- Schedule 80 PVC must be used in between fused disconnect and MSP - only showing 2 hots and neutral
- All other conduit can be EMT
For all Load Side Taps:
- Schedule 80 PVC must be used in between disconnect and MSP
- Custom Placards Required
- 0