Net Metering AllowedYes
NEM TypeAnnual
Line Taps AllowedNo
Load Taps AllowedNo
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
Yes
NEM Type
Annual
TOU Utility
No
Post Solar Billing Method
Export Rate
Solar Export Type
Other
Solar Export Value Notes
0.00
Net Excess Generation Notes

Net Metering: If the kWhs generated by the net-metering facility and fed back to OMLP exceed the kWhs supplied by OMLP to the net-metering customer during the applicable billing period, OMLP shall credit the net-metering customer with any accumulated net excess

generation in the next applicable billing period, month-to-month, until the close of the annual billing cycle, at which time any net excess generation credit shall expire and shall zero out. 

Rebates Offered
No
Deregulated
No

Interconnection & taps

Approval Req To Install
Yes
Line Taps Allowed
No
Load Taps Allowed
No
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
No

System size & offset

System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes

MAXIMUM SYSTEM SIZE: 10 kW DC or AC or 100% offset (whichever is less)

No Exception - Anything above 10 kW is not eligible for Net Metering

Offset Calc Tool
Historical Usage

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
AC Disconnect Required
Yes
AC Disconnect Labeling
Visible Lockable Labeled Disconnect
Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs
  • Utility requires STRUCTURAL engineering signed by a Licensed Professional Engineer
SLD Reqs
  • Utility requires all panels to be minimum 200A service. Future projects will need a 200A min service/upgrade prior to PV installation
Meter Num Req SLD 3LD
No
ESID Num Req SLD 3LD
No
Rate Schedule Link
link
Website
link
Phone
(870) 563-5245

Other details

Revision Required
Yes
Mod Swap Requires Planset