Solar Sanity Checksolar, decoded Independent. Nothing you type leaves your browser.

LID - Lathrop Irrigation District

California Utility Interconnection & net metering rules
Net Metering Allowed0
Line Taps Allowed0
Load Taps Allowed0
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
0
TOU Utility
0
Post Solar Billing Method
Export Rate
Net Excess Generation Notes

WGC allows customers to install solar on their site and use the energy generated from the site to power their home. When the solar panels produce exactly what the customer uses, there will be no energy charges added to the customer’s bill (all applicable fees and taxes will apply and must be paid monthly). During times when the solar panels produce more electricity than the customer uses, the net surplus that flows back to the power grid is credited at the WGC rate - $0.04 cents per kilowatt hour. When the solar panels don’t produce enough power for the customer’s home, WGC customers will pay the same rate as other LID electric customers.

If the energy produced by the system is greater than the energy you are using at that time, then the excess energy produced is credited to that month’s bill at the WGC rate - $0.04 cents per kilowatt hour.

Rebates Offered
0
Deregulated
0
Allows Standby
1

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
Percentage
Offset Value
125
Offset Calculation Basis
Historical
Offset Calculation Period
12
Industry Standard Watts Sqft
2
Utility Specific Adjustments
  • It is recommended to size the system below 20 kW AC as going over 20 kW will have longer timeline (at least 6 months) and fee of $1,800.00
System Offset Notes


Offset Calc Tool
CSI

Metering & disconnect

Production Meter Required
Yes
Production Meter Position
Inv-PM-Disco-POI
Production Meter Labeling
Production Meter
AC Disconnect Required
Yes
AC Disconnect Labeling
Visible Lockable Labeled Disconnect
Allowed Meter Adapter
Tesla Backup Switch

Plans & docs

Site Plan Reqs

All Projects

  • Production Meter and Disconnect must be located in front of fence for 24 hour access
SLD Reqs

Existing Systems

  • Existing (N) and (E) systems must be combined to share one production meter. This includes battery projects
Electrical Stamp Required
0
Equipment Approvals
California Energy Commission
Meter Num Req SLD 3LD
0
ESID Num Req SLD 3LD
0
Website
link
Phone
209-323-5000 ext. 1417

Other details

Restrict Inspection
0
Revision Required
1
Mod Swap Requires Planset
1
Address ID
110287
Express Planset Eligible
No