Pacific Power (CA)

California Utility Interconnection & net metering rules

Spot something wrong?

Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.

Report a correction
Net Metering AllowedYes
Supply Side Taps AllowedNo
Line Taps AllowedNo
Load Taps AllowedNo

Net metering & export

Net Metering Allowed
Yes
Post Solar Billing Method
Net Metering
Rebates Offered
No

Interconnection & taps

Approval Req To Install
Yes
Supply Side Taps Allowed
No
Line Taps Allowed
No
Load Taps Allowed
No
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
Yes

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
Allowed Meter Adapter
ConnectDER,Tesla Backup Switch

Plans & docs

Site Plan Reqs

Show distance from AC Disconnect to Utility Meter (UM).

- CA: within 3 feet from the UM

- OR: within 10 feet from the UM

- WA: within 3 feet from the UM

SLD Reqs

A one-line diagram showing:

- The location of Utility Meter (UM)

- The location of the disconnect switch

FOR BATTERIES: - ESS DISCONNECT REQUIRED

Install Reqs

After installation, schedule an appointment to have the Net Meter set by calling.

Submit a photo of the installed placards with Request for Inspection.

Placards

.

Website
link
Phone
1-800-625-6078; 203-813-7496
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with Pacific Power (CA) before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.