PG&E - Pacific Gas and Electric Company

California Utility Interconnection & net metering rules

Spot something wrong?

Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.

Report a correction
Net Metering AllowedYes
NEM TypeAnnual
Supply Side Taps AllowedNo
Line Taps AllowedNo
Load Taps AllowedYes
AC Disconnect RequiredSituational

Net metering & export

Net Metering Allowed
Yes
NEM Type
Annual
TOU Utility
Yes
Post Solar Billing Method
Export Rate
Solar Export Type
Other
Net Excess Generation Notes
  • Excess credits at the end of each month roll over from month to month within the annual true-up period.
  • At the end of each annual true-up period, any remaining kWh credits are paid at the rate set by the CA CPUC, typically between $.02-$.04/kWh.
Rebates Offered
Yes
Deregulated
No
Allows Standby
Yes

Interconnection & taps

Approval Req To Install
No
Supply Side Taps Allowed
No
Line Taps Allowed
No
Load Taps Allowed
Yes
Tap Criteria
  • ONLY protected load side taps are acceptable by the utility
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
Yes

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes


Offset Calc Tool
CSI

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
AC Disconnect Required
Situational
AC Disconnect Criteria

AC disconnect required in the following situations

  • Line side connection (above main breaker)
  • 3-Phase service
  • Meter-Panel is transformer rated
  • Meter-Panel rated at > 320a

If none of these apply, we do not need an AC disconnect.

AC Disconnect Labeling
Visible Lockable Labeled Disconnect
Meter Spot Required
Yes
Allowed Meter Adapter
GMA,Tesla Backup Switch

Plans & docs

Site Plan Reqs

All Projects

  • If the project requires an AC disconnect, the disconnect must be within 10' of the utility meter.
  • AC disconnects are not required for every project. Any trenching should only be done if the disconnect is absolutely necessary.

GMA Projects

  • MUST have a 36" clearance from gas meter -- No exceptions or variances will be given.
  • Overhead service not allowed.

Battery Projects

  • If we install batteries in the garage, provide elevation detail showing batteries will be mounted 3' above a finished floor OR provide bollards for protection from vehicles.
  • Interior mounted batteries require heat detectors in accordance with section R314.
  • If heat detectors are needed, provide spec sheets and CA State Fire Marshal listing.
SLD Reqs

GMA Projects

  • Main Service Panel cannot be rated greater than 125A for a GMA tie in.
  • If there is an existing system, new system cannot tie in with a GMA.
  • Battery projects, including non-backup, cannot tie in with a GMA
  • Use #6 Cu in ¾" LFNC conduit between Disconnect and meter adapter

Existing Systems

  • MUST show model numbers of existing modules/inverters
  • MUST SHOW existing system BOS / AC Disconnect (needs to be included on the title block)
  • Tying existing solar into a GMA is not allowed. For GMA guidelines, See link

Battery Projects

  • Please add the model number verbiage immediately next to the battery
  • Example: (1) Tesla Inc. / AC Powerwall 1092170-XX-Y [240V] [SI1-JUN20]
  • Example: Gateway 1118431-XX-X [CRD-PCS Non-Export]
Install Reqs
  • POI is required to be below the main breaker on the customer load side.
Placards

Existing Systems

  • Remove the old placard and replace it with a new one that includes both the existing and new systems.
  • Ensure components from both systems are shown in the updated design.
  • If existing arrays do not meet current California Energy Commission (CEC) RSD requirements, place a dotted line around non-compliant arrays include a note stating: "Existing arrays will remain energized upon RSD activation."

AC Disconnect

  • If a project has 2 or more AC disconnects (new or existing), on the placard label each disconnect clearly, e.g., “AC Disconnect 1 of X,” “AC Disconnect 2 of X,” etc.
  • In the placard page, include label for all AC disco "AC Disconnect 1 of X" / " AC Disconnect 2 of X " and etc.
  • If any AC disconnect is more than 10 ft from the PG&E meter, include a site map placard, regardless of the number of disconnects
Electrical Stamp Required
No
Meter Num Req SLD 3LD
No
ESID Num Req SLD 3LD
No
Site Plan Notes
  • INCLUDE NOTE IF AC DISCO IS REQUIRED [AC DISCONNECT MUST BE WITHIN 10' OF THE UTILITY METER]
Label Page Notes


Cover Page Notes


Electrical Diagram Notes

Battery [Producers storage device(s) will not cause the Host Load to exceed its normal peak demand. Normal peak demand is defined as the highest amount of power required from the Distribution System by Producers complete facilities without the influence or use of the energy storage device(s). - The customers solar generating system, including an energy storage system if installed, connected to the GMA, will have no more than a maximum rating of 14.0 kilowatts (kW) at 240 volts (V) and does not produce a total of more than 60 amps]

Rate Schedule Link
link
Website
link
Phone
(877) 743-4112

Other details

Revision Required
Yes
Mod Swap Requires Planset
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with PG&E - Pacific Gas and Electric Company before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.