Glenwood Springs
Net metering & export
- Net Metering Allowed
- 1
- Post Solar Billing Method
- Net Metering
- Net Excess Generation Notes
Monthly excess generation. If the customer-generator generates electricity in excess of the customer-generator’s monthly consumption, all such excess energy, expressed in kilowatt-hours, shall be carried forward from month to month and credited at a ratio of one to one against the customer-generator’s energy consumption, expressed in kilowatt-hours, in subsequent months.
Annual excess generation. Within sixty days after the end of each annual period, or within sixty days after the customer-generator terminates its retail service, the City shall account for any excess energy generation, expressed in kilowatt-hours, accrued by the customer-generator and shall credit such excess generation to the customer-generator in a manner deemed appropriate by the City.
- Rebates Offered
- 0
- Deregulated
- 0
Interconnection & taps
- Approval Req To Install
- Yes
- Interconnection Level
- 3
- Line Taps Allowed
- 0
- Load Taps Allowed
- 0
- Automatic Transformer Upgrade Size
- 0
System size & offset
- System Size Restrictions
- 10
- System Size Restriction Type
- AC kW
- System Size Battery Included
- 0
- System Size Includes Existing Systems
- 0
- Offset Type
- Combination
- Offset Value
- 120
- Offset Calculation Basis
- Historical
- Offset Calculation Period
- 12
- Industry Standard Watts Sqft
- 2
- System Offset Notes
Metering & disconnect
- Production Meter Required
- No
- Production Meter Position
- N/A
- Production Meter Labeling
- N/A
- AC Disconnect Required
- Yes
- AC Disconnect Labeling
- Visible Lockable Labeled Disconnect
- Allowed Meter Adapter
- None
Plans & docs
- SLD Reqs
The 1-line electrical diagram shall show all wiring, connecting point and protective devices for the selected equipment components at this site.
- Placards
The AC outlet supply shall be wired to an outside disconnect, labeled, “WARNING!! DUAL POWER SUPPLY”, installed adjacent to or at the main point of service disconnect.
- Electrical Stamp Required
- 0
- Meter Num Req SLD 3LD
- 0
- ESID Num Req SLD 3LD
- 0
- Website
- link
- Phone
- (970) 384-6352
Other details
- Restrict Inspection
- 0
- Address ID
- 175697
- Express Planset Eligible
- Yes