Report a correctionNet metering & export
- Net Metering Allowed
- Yes
- NEM Type
- Monthly
- TOU Utility
- No
- Post Solar Billing Method
- Net Metering
- Solar Export Type
- Fixed kWh
- Solar Export Rate
- 0.12
- Rebates Offered
- No
- Deregulated
- No
Interconnection & taps
- Approval Req To Install
- Yes
- Line Taps Allowed
- No
- Load Taps Allowed
- No
- Automatic Transformer Upgrade Size
- 0
- Meter Aggregation Allowed
- No
System size & offset
- System Size Restrictions
- 25
- System Size Restriction Type
- AC kW
- System Size Battery Included
- No
- System Size Includes Existing Systems
- No
- Offset Type
- Combination
- Offset Value
- 110
- Offset Calculation Basis
- Average
- Offset Calculation Period
- 24
- Industry Standard Watts Sqft
- 2
- System Offset Notes
System need to be under 25 kW for Residential, 500 kW for Non-Residential, 100 KW for Farm
25 kw for residential, 110% of last 2 years consumption
- Offset Calc Tool
- Historical Usage
Metering & disconnect
- Production Meter Required
- No
- Production Meter Position
- N/A
- Production Meter Labeling
- N/A
- Allowed Meter Adapter
- None
Plans & docs
- Placards
The Generator Owner will install a warning label in a conspicuous place on their electric meter or meter box to notify the Company personnel that there is a generator source installed on the load side of the meter. The warning label shall not be placed in a location that would interfere with the ability of Company personnel to read the electric meter. The Company will provide the warning label to the Generator Owner. The warning label must be placed before the generation can be interconnected.
- Website
- link
- Phone
- (302) 323-2330