City of Blountstown

Florida Utility Interconnection & net metering rules
Net Metering Allowed1
NEM TypeMonthly
Line Taps Allowed0
Load Taps Allowed0
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
1
NEM Type
Monthly
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

Meter readings shall be taken monthly. Excess generation shall be purchased by the city in the form of a credit on the customers bill. Each billing cycle, customer shall be credited for any excess energy generated. This credit will be in accordance with the avoided energy cost. Credit for excess generation produced shall accumulate and be applied to the customers consumption bill through the end of the calendar year. In the last billing cycle of the year, any remaining account credit balance will be paid by the city to the customer. The city will issue an IRS 1099-MISC form totaling all monthly credits for the previous year to customers with total credits of $600 or greater.

Rebates Offered
0
Allows Standby
1

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes


Metering & disconnect

Production Meter Required
Yes
Production Meter Position
Inv-Disco-PM-POI
Production Meter Labeling
Production Meter
AC Disconnect Required
Yes
AC Disconnect Labeling
Utility Disconnect Switch

Plans & docs

Site Plan Reqs

Standard

SLD Reqs

Standard - See uploaded example

Electric Service Reqs

IEEE 1547

UL 1741

Install Reqs

AC Disconnect Required

  • Must be a manual disconnect switch of the visible load break type to provide separation point between the AC power output of the system and the cities wiring
  • Must be readily accessible to the utility and capable or being locked in the open position

PV Meter Required (installer to provide socket)

Electrical Stamp Required
0
Equipment Approvals
California Energy Commission
Meter Num Req SLD 3LD
0
ESID Num Req SLD 3LD
0

Other details

Revision Required
1
Address ID
10384075
Express Planset Eligible
No