Coweta-Fayette EMC

Georgia Utility Interconnection & net metering rules

Spot something wrong?

Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.

Report a correction
Net Metering AllowedYes
NEM TypeMonthly
Supply Side Taps AllowedYes
Line Taps AllowedYes
Load Taps AllowedYes
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
Yes
NEM Type
Monthly
TOU Utility
No
Post Solar Billing Method
Net Metering
Solar Export Type
Avoided Cost
Solar Export Rate Approx
0.0375
Solar Export Value Notes
per kWh
Net Excess Generation Notes

Production that exceeds the customers' monthly usage will be credited at the Excess Generation Rate.

The monthly administrative fee is $4.00, added to the $20 service charge

If there is an excess of kilowatts used per billing cycle, they are purchased at an avoided cost of $.0296 cents per kilowatts

Rebates Offered
No
Deregulated
No
Allows Standby
No

Interconnection & taps

Approval Req To Install
Yes
Supply Side Taps Allowed
Yes
Line Taps Allowed
Yes
Load Taps Allowed
Yes
Tap Criteria

Line Side taps allowed but not in meter can.

Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
10
System Size Restriction Type
AC kW
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes

The capacity of distributed generation facilities used by residential members shall not exceed 10 kW. The capacity of distributed generation facilities used by non-residential members shall not exceed 100 kW.

Metering & disconnect

Production Meter Required
No
AC Disconnect Required
Yes
Allowed Meter Adapter
None

Plans & docs

SLD Reqs

A single-line diagram is required showing the Customer’s installation of its generating facilities and the interconnection to Coweta-Fayette EMC’s system. Devices such as the service panel, disconnect switch, inverters, all generators, circuit breakers, etc. must contain the electrical rating and operating voltages.


Line Side taps allowed but not in meter can.

Website
link
Phone
(770) 502-0226

Other details

Revision Required
No
Mod Swap Requires Planset
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with Coweta-Fayette EMC before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.