Habersham EMC

Georgia Utility Interconnection & net metering rules

Spot something wrong?

Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.

Report a correction
Net Metering AllowedYes
NEM TypeMonthly
Line Taps AllowedNo
Load Taps AllowedNo

Net metering & export

Net Metering Allowed
Yes
NEM Type
Monthly
TOU Utility
Yes
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

Production that exceeds the customers' monthly usage will be credited at the Excess Generation Rate.

0.052 per kWh

$15.00 per month administrative charge

Rebates Offered
No
Deregulated
No

Interconnection & taps

Approval Req To Install
No
Line Taps Allowed
No
Load Taps Allowed
No
Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
10
System Size Restriction Type
AC kW
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes

The capacity of a distributed generation facility used by residential consumers shall not exceed 10 kW and the capacity of a distributed generation facility used by a commercial consumer shall not exceed 100 kW.

Metering & disconnect

Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs

Describe the project’s planned operating mode (e.g., combined heat and power, peak shaving, etc.), and its address or grid coordinates

SLD Reqs

Detailed one-line diagram of the proposed facility, all applicable elementary diagrams, major equipment, (generators, transformers, inverters, circuit breakers, protective relays, etc.) specifications, test reports, etc., and any other applicable drawings or documents necessary for the proper design of the interconnection

No production meter, utility meter is bi-directional

Website
link
Phone
(706) 754-2114
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with Habersham EMC before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.