Hart EMC
Spot something wrong?
Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.
Report a correction Net Metering AllowedYes
NEM TypeMonthly
Line Taps AllowedNo
Load Taps AllowedNo
Net metering & export
- Net Metering Allowed
- Yes
- NEM Type
- Monthly
- TOU Utility
- Yes
- Post Solar Billing Method
- Net Metering
- Net Excess Generation Notes
The purchase rate for a DG facility rated 10kW or less as of the effective date of this Rider is: All kWh $0.060 per kWh. The purchase rate for a DG facility rated greater than 10kW up to 100kW as of the effective date of this Rider is: All kWh $0.035 per kWh
- Rebates Offered
- No
- Deregulated
- No
Interconnection & taps
- Approval Req To Install
- Yes
- Line Taps Allowed
- No
- Load Taps Allowed
- No
- Automatic Transformer Upgrade Size
- 0
- Meter Aggregation Allowed
- Yes
System size & offset
- System Size Restrictions
- 0
- System Size Restriction Type
- No Restrictions
- System Size Battery Included
- No
- System Size Includes Existing Systems
- No
- Offset Type
- No Restrictions
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
Metering & disconnect
- Production Meter Required
- No
- Production Meter Position
- N/A
- Production Meter Labeling
- N/A
- Allowed Meter Adapter
- None
Plans & docs
- SLD Reqs
Site Information, Solar Array Information, Disconnect Locations, Wiring Sizes.
- Website
- link
- Phone
- (800) 241-4109