Sawnee EMC

Georgia Utility Interconnection & net metering rules
Net Metering Allowed1
NEM TypeMonthly
Line Taps Allowed0
Load Taps Allowed1

Net metering & export

Net Metering Allowed
1
NEM Type
Monthly
TOU Utility
0
Post Solar Billing Method
Export Rate
Solar Export Type
Avoided Cost
Net Excess Generation Notes

For all Cooperative members who have a Distributed Generation Facility interconnected with the Cooperative on or before January 1, 2024, Excess Net Energy will be settled on a monthly basis and for all Cooperative members who have a Distributed Generation Facility interconnected with the Cooperative on or after January 2, 2024, Excess Net Energy will be settled instantaneously.

Rebates Offered
0
Deregulated
0
Allows Standby
0

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
1
Line Taps Allowed
0
Load Taps Allowed
1
Tap Criteria

Load side tap allowed IF the service is a meter/main combo

Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
10
System Size Restriction Type
AC kW
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes


Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs

• We need the point of common coupling listed on the SLD and site plan.

SLD Reqs
  • The point of common coupling listed on the SLD and site plan.

Battery

  • Battery systems require their own AC disconnect or an AC disconnect must be in place between Gateway and meter.
Placards

Add Electrical Shock Warning placard to the meter base

Website
link
Phone
(770) 887-2363

Other details

Restrict Inspection
0
Revision Required
0
Mod Swap Requires Planset
1
Address ID
195020
Express Planset Eligible
Yes