Net Metering AllowedYes
NEM TypeMonthly
Line Taps AllowedNo
Load Taps AllowedNo

Net metering & export

Net Metering Allowed
Yes
NEM Type
Monthly
TOU Utility
No
Post Solar Billing Method
Net Metering
Net Excess Generation Notes
Any electrical energy generated by the Net Metering System that is surplus to the simultaneous electrical usage of the Customer is termed "excess energy". This electrical energy flows into the City's system and is used to serve other Customers.
Rebates Offered
No
Deregulated
No

Interconnection & taps

Approval Req To Install
No
Line Taps Allowed
No
Load Taps Allowed
No
Automatic Transformer Upgrade Size
0

System size & offset

System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes
Nameplate generating capacity of not more than 25kW
Offset Calc Tool
PV Watts

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
Allowed Meter Adapter
None