Net metering & export
- Net Metering Allowed
- 1
- NEM Type
- Annual
- TOU Utility
- 0
- Post Solar Billing Method
- Net Metering
- Net Excess Generation Notes
For energy delivered by the Utility to the customer at the meter, as reflected in the meter reading, shall be billed at the Utility’s appropriate full retail energy rate. For any excess energy generated by the customer from an approved on-site generating facility and delivered by the customer to the Utility at the meter, as reflected in the meter reading, a credit shall be created and applied to the customer’s bill based upon the lesser of the full retail energy rate for the customer class and the avoided cost of energy.
The City shall carry over any unused credits earned and apply those credits to subsequent billing periods to offset usage based electric energy (kWh) charges only for electric energy supplied to the customer by the Utility until all credits are used or until the end of the annual period. The annual period shall end each year on April 30.
- Rebates Offered
- 0
Interconnection & taps
- Approval Req To Install
- Yes
- Interconnection Level
- 3
- Supply Side Taps Allowed
- 0
- Line Taps Allowed
- 0
- Load Taps Allowed
- 0
- Automatic Transformer Upgrade Size
- 0
System size & offset
- System Size Battery Included
- 0
- System Size Includes Existing Systems
- 0
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
- System Offset Notes
- The system must be sized within the customer's 36 months of historical energy usage
- Offset Calc Tool
- Historical Usage
Metering & disconnect
- Production Meter Required
- No
- Production Meter Position
- N/A
- Production Meter Labeling
- N/A
- Allowed Meter Adapter
- None
Plans & docs
- Site Plan Reqs
- AC disconnect must be accessible to the utility 24/7
- SLD Reqs
- AC disconnect: safety manual disconnect switch of the visible load break type