Solar Sanity Checksolar, decoded Independent. Nothing you type leaves your browser.

Southwestern Electric Coop

Illinois Utility Interconnection & net metering rules
Net Metering Allowed0
Supply Side Taps Allowed0
Line Taps Allowed0
Load Taps Allowed0
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
0
TOU Utility
0
Post Solar Billing Method
Export Rate
Solar Export Type
Avoided Cost
Net Excess Generation Notes
  • A dual register meter will record both the kWh purchased and the kWh generated onto our system. Both registers are read at the beginning of the month and the kWh purchased are calculated at your current rate while the kWh generated onto our system are calculated at our avoided cost.
  • If the dollar amount of credit is greater than the dollar amount of your energy charge, the difference will be put into your “cogen bank” to be applied in future months as needed. The bank resets on April 30th of each year. Any remaining balance will be cleared on this date.
Rebates Offered
0
Deregulated
0
Allows Standby
1

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Supply Side Taps Allowed
0
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
AC Disconnect Required
Yes
AC Disconnect Labeling
Utility AC Disconnect
Meter Spot Required
0
Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs
  • A site plan is not required for this utility
SLD Reqs
  • A lockable disconnect is to be provided in close proximity (within 10') of the revenue meter so we can disconnect the inverter, if necessary. The disconnect will need to be visible from the meter
  • Must include size in AC and DC, disconnect location from the meter (in ft), and location of signage.
  • Singular Point of Interconnection: All generation sources must be able to be shut off by a singular lockable, knife-handled disconnect.
Install Reqs
  • The disconnect is required to have a visible open point.
  • Breaker type disconnects are not allowed.
  • Disconnects are not allowed to be attached to SWECI transformer poles or meter poles.
  • The inverter is not to be interconnected to the utility until it has passed commissioning and a dual register meter has been installed.
Placards
  • Label the disconnect as an interconnected generation source.
  • If panels are on a different building than the utility meter, the label must also show the disconnect’s location.
Electrical Stamp Required
0
Equipment Approvals
California Energy Commission
Meter Num Req SLD 3LD
0
ESID Num Req SLD 3LD
0
Website
link
Phone
(800) 637-8667

Other details

Restrict Inspection
0
Address ID
664425
Express Planset Eligible
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with Southwestern Electric Coop before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.