Flint Hills Rural ECA

Kansas Utility Interconnection & net metering rules
Net Metering Allowed1
NEM TypeMonthly
Line Taps Allowed0
Load Taps Allowed0
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
1
NEM Type
Monthly
TOU Utility
0
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

To the extent the net consumption is negative (i.e. Customer-generator produced more kWh during the billing period than the Cooperative supplied), the Customer-generator will pay applicable Customer Charges, Demand Charges, and/or any Minimum Charges that would otherwise be applicable to the Customer under the standard rate; and the excess electric energy shall be retained by the supplier as a contribution to fixed costs associated with owning and maintaining the facilities required to provide electric service when the Customer-generator cannot meet its own supply needs

Rebates Offered
0
Deregulated
1
Allows Standby
0

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
0

System size & offset

System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes

Per utility regarding 12 months consumption history

"If a prospective customer is not able to provide you with his 12-month usage history, I would recommend that you contact me to calculate the appropriate sizing per our formula to save you from doing all the work to send the application and plans for a system that is larger than we will approve for interconnection. We do have some line sections that have reached the maximum interconnection and no further interconnection is allowed, so that’s something else that I can check proactively."

Offset Calc Tool
Historical Usage

Metering & disconnect

Production Meter Required
Yes
Production Meter Position
Inv-Disco-PM-POI
Production Meter Labeling
Production Meter
AC Disconnect Required
Yes
AC Disconnect Labeling
Utility Disconnect Switch
Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs

Standard

SLD Reqs

The one-line diagram must contain a manual disconnect and a production side meter.

Electric Service Reqs

Review Attachment 3 - Certification Codes and Standards uploaded to the files

Install Reqs

AC Disconnect Required

Production Meter Socket Required (Utility installs the meter at PTO inspection)

Placards

No additional requirements beyond NEC code

Electrical Stamp Required
0
Equipment Approvals
California Energy Commission
Meter Num Req SLD 3LD
0
ESID Num Req SLD 3LD
0

Other details

Express Planset Eligible
No