Eversource Energy (Eastern MA)

Massachusetts Utility Interconnection & net metering rules
Net Metering Allowed1
NEM TypeMonthly
Supply Side Taps Allowed1
Line Taps Allowed1
Load Taps Allowed1
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
1
NEM Type
Monthly
TOU Utility
0
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

Excess generation at the end of each month is credited at the applicable retail electricity rate and rolled forward to future bills as a dollar credit. This credit rolls forward indefinitely to future bills but cannot be "cashed out".

Rebates Offered
1
Deregulated
1
Allows Standby
1

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Supply Side Taps Allowed
1
Line Taps Allowed
1
Load Taps Allowed
1
Automatic Transformer Upgrade Size
20
Automatic Transformer Upgrade Size Type
kW AC

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
1
System Size Includes Existing Systems
0
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
Inverter Oversize Restrictions
0
System Offset Notes


Metering & disconnect

Production Meter Required
Situational
Production Meter Criteria

Production Meter (SMART meter)

  • Required for: Cash, Loan, Aura, Aura+
  • Not required for: Lease projects
  • Wire inverter on bottom side and utility on top side
  • Only 1 production meter per project
  • Second meter allowed only if 12 months have passed since existing system PTO
Production Meter Position
Inv-Disco-PM-POI
Production Meter Labeling
Production Meter
AC Disconnect Required
Yes
AC Disconnect Labeling
Visible Lockable Labeled Disconnect
Meter Spot Process
  • Any Before digging, call them at 1-888-DIG-SAFE () to get underground utilities marked. For more info, visit www.digsafe.com.
Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs
  • Show parcel boundaries (property/lot lines).
  • Show distance from UM to Eversource Transformer in feet. See "Utility Meter to Transformer" in Files section of this page.
  • Include Peak/Max Output
SLD Reqs
  • Projects over 15 kW AC require an EE stamp.
  • Specify make and model of equipment. Do not use “Min 60A” for a disconnect size.
  • Load Side Tap does not require 2 disconnects as long as Fused Disconnect is accessible outside.
  • Include Peak/Max Output
Electric Service Reqs
  • Follow meter wiring and labeling guidelines. See "Wiring Sample" in Files section of this page.
  • Allowable Meter Sockets: See "Approved Metering Equipment" in Files section of this page.
  • Will require a meter relocation whenever the utility meter is located on the interior, or in any cabinets
  • Max allowable height for the utility meter is 5'5" from grade, measured from the center of the meter.
Electrical Stamp Required
0
Meter Num Req SLD 3LD
0
ESID Num Req SLD 3LD
0
Site Plan Notes

All Jobs [AC Disconnect shall be 24/7 accessible, within 10 feet of, within visible sight of, and on same wall as the Utility Meter (Exception for pedestal meters)]

Website
link
Phone
413-787-1087

Other details

Restrict Inspection
1
Revision Required
1
Address ID
1094111
Express Planset Eligible
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with Eversource Energy (Eastern MA) before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.