Solar Sanity Checksolar, decoded Independent. Nothing you type leaves your browser.

Eversource Energy (Western MA)

Massachusetts Utility Interconnection & net metering rules
Net Metering Allowed1
NEM TypeMonthly
Supply Side Taps Allowed1
Line Taps Allowed1
Load Taps Allowed1
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
1
NEM Type
Monthly
TOU Utility
0
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

Excess generation at the end of each month is credited at the applicable retail electricity rate and rolled forward to future bills as a dollar credit. This credit rolls forward indefinitely to future bills but cannot be "cashed out".

Rebates Offered
1
Deregulated
1
Allows Standby
1

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Supply Side Taps Allowed
1
Line Taps Allowed
1
Load Taps Allowed
1
Tap Criteria
  • LST does not require 2 disconnects as long as Fused Disco is accessible outside.
Automatic Transformer Upgrade Size
20
Automatic Transformer Upgrade Size Type
kW AC

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
Utility Specific Adjustments
  • Please try to be <15KW AC system size whenever possible. For example: Please use mix of 7.6KVA and 5.7KVA to be under 15KW AC rather than using two 7.6KVAs as long as finance inverter OD ratio is under the limit. This will avoid Level 2 application and reduce approval times. Also avoids EE stamp.
  • Eversource Hosting Capacity Map
System Offset Notes


Metering & disconnect

Production Meter Required
Situational
Production Meter Criteria

Production Meter (SMART meter)

  • Required for: Cash, Loan, Aura, Aura+
  • Not required for: Lease projects
  • Wire inverter on bottom side and utility on top side
  • Only 1 production meter per project
  • Second meter allowed only if 12 months have passed since existing system PTO
Production Meter Position
Inv-Disco-PM-POI
Production Meter Labeling
Production Meter
AC Disconnect Required
Yes
AC Disconnect Labeling
Visible Lockable Labeled Disconnect
Meter Spot Process
  • Before you dig, call them at 1-888-DIG SAFE () to get underground utilities marked. For more info, visit www.digsafe.com.
Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs
  • The module: NE SOLAR: NESE370-60MH is not an acceptable module in this utility as it does not meet their safety standards.
  • Show parcel boundaries (property/lot lines).
  • Show distance from UM to Eversource Transformer in feet. See "Utility Meter to Transformer" in Files section of this page. If proximity requirements cannot be met, request a variance from Eversource. If a variance is granted, placard the UM stating that there is solar generation on site, and show the location of the AC Disconnect.
  • Placard the AC Disconnect stating that it is for solar generation.
  • Include Peak/Max Output
SLD Reqs
  • Include Peak/Max Output
  • Projects over 15 kW AC require an EE stamp
Electric Service Reqs
  • Will require a meter relocation whenever the utility meter is located on the interior, or in any cabinets
Install Reqs


Placards
  • If AC Disconnect cannot be 24/7 accessible, within 10 feet of, within visible sight of, and on same wall as Utility Meter, request a variance from Eversource. If a variance is granted, placard the UM stating that there is solar generation on site, and show the location of the PM and AC Disconnect. Placard the PM and AC Disconnect stating that they are for solar generation.
Electrical Stamp Required
0
Meter Num Req SLD 3LD
0
ESID Num Req SLD 3LD
0
Site Plan Notes

All Jobs [AC Disconnect shall be 24/7 accessible, within 10 feet of, within visible sight of, and on same wall as Utility Meter // AC Disconnect will be labeled with the location of the Utility Meter. A placard on the Utility Meter will show the location of the Disconnect.]

Electrical Diagram Notes

All Jobs [AC Disconnect shall be 24/7 accessible, within 10 feet of, within visible sight of, and on same wall as Utility Meter // AC Disconnect will be labeled with the location of the Utility Meter. A placard on the Utility Meter will show the location of the Disconnect.]

Website
link
Phone
(888) 783-6616

Other details

Restrict Inspection
1
Revision Required
1
Address ID
245164
Express Planset Eligible
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with Eversource Energy (Western MA) before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.