Unitil (MA)
Net Metering Allowed1
NEM TypeMonthly
Supply Side Taps Allowed1
Line Taps Allowed1
Load Taps Allowed1
Net metering & export
- Net Metering Allowed
- 1
- NEM Type
- Monthly
- Post Solar Billing Method
- Net Metering
- Net Excess Generation Notes
The Company will notify the Host Customer within 30 days of the filing of Schedule Z whether it will allocate or purchase Net Metering Credits. If the Company elects to purchase Net Metering Credits, the Company will render payment by issuing a check to the Host Customer each Billing Period, unless otherwise agreed in writing by the Host Customer and Company.
- Rebates Offered
- 1
- Allows Standby
- 1
Interconnection & taps
- Approval Req To Install
- Yes
- Interconnection Level
- 3
- Supply Side Taps Allowed
- 1
- Line Taps Allowed
- 1
- Load Taps Allowed
- 1
- Automatic Transformer Upgrade Size
- 0
System size & offset
- System Size Restrictions
- 0
- System Size Restriction Type
- No Restrictions
- System Size Battery Included
- 0
- System Size Includes Existing Systems
- 0
- Offset Type
- No Restrictions
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
- Utility Specific Adjustments
Net Metering & System Size Rules
- โค 10 kW AC โ Qualifies for 100% Net Metering
- > 10 kW AC โ Not eligible for NEM (will be processed as QF until further notice)
- > 10 kW AC with MassACA approval โ May qualify for 60% Net Metering credit
Process Type
Simplified Process
- Single-phase UL-listed inverter systems
- โค 15 kW AC (single phase)
- โค 25 kW AC (three phase)
EPD/STD Process
- 15 kW AC (single phase)
- 25 kW AC (three phase)
- Energy storage systems
- May require transformer upgrades
- System Size Justification
- Load Justification
- System Offset Notes
Metering & disconnect
- Production Meter Required
- Situational
- Production Meter Criteria
Production Meter (SMART meter)
- Required for: Cash, Loan, Aura, Aura+
- Not required for: Lease projects
- Wire inverter on bottom side and utility on top side
- Only 1 production meter per project
- Second meter allowed only if 12 months have passed since existing system PTO
- Production Meter Position
- Inv-Disco-PM-POI
- Production Meter Labeling
- Production Meter
- Allowed Meter Adapter
- None
Plans & docs
- Site Plan Reqs
- Include location of interconnection transformer, interconnecting device, point of common coupling, point of interconnection, line extension
- Show the location of all DG equipment, existing service meter, and driveway or access to facility
- AC Disconnect must be installed next to the existing utility meter. They must be moved to be located next to the existing UM
Battery Projects
- An ESS Questionnaire must be filled out by design for all battery projects. A blank copy of this form is uploaded to the Files section below titled "Unitil ESS Questionnaire."
- SLD Reqs
- Show all switching and protective devices and the tie point to utility system. The one line should include all current transformers and voltage transformers with all ratios
- Electric Service Reqs
- Install Reqs
Meter Location
- Must be outside (unless pre-approved electrical room)
- Place on front 1/3 of home, driveway gable side, or customer-owned structure
- Must be accessible to Unitil personnel
- No fences, obstructions, or special access needed
- Location requires prior Unitil approval
Clearance Requirements
- Meter height: 5 - 5.5 feet above finished grade
- Maintain 3 ft wide ร 3 ft deep clear working space
- Keep area clear of landscaping or obstructions
- Follow National Electrical Code clearance rules
- Electrical Stamp Required
- 0
- Website
- link
- Phone
- (603) 773-6480
Other details
- Restrict Inspection
- 0
- Address ID
- 126258
- Express Planset Eligible
- Yes